Section 8

Project Risk Management

1 QUESTION

What is Project Risk Management?

ANSWER

The processes concerned with planning, identifying, analyzing, responding, and monitoring and controlling project risk. It also includes maximizing the results of positive events as well as minimizing the consequences of adverse events to project objectives.

[Planning, Monitoring and Controlling]

2 QUESTION

How is Monte Carlo analysis used in schedule simulations?

ANSWER

To “perform” the project many times in order to provide a statistical distribution of the calculated results. For a schedule risk analysis, the schedule network diagram and duration estimates are used.

[Planning]

3 QUESTION

Generally speaking, in what project phase are risk and opportunity greater, by the widest margin, than the amount at stake?

ANSWER

Concept phase.

[Planning]

4 QUESTION

What is a reserve?

ANSWER

A provision (usually time or money) in the project management plan to mitigate cost and/or schedule risk. Typically, there are two reserves on any project: management reserve and contingency reserve.

[Planning]

5 QUESTION

What is the purpose of a risk rating in the perform qualitative risk analysis process?

ANSWER

To focus the project team’s efforts on developing responses for those risks that have the highest probability of impact and occurrence.

[Planning]

6 QUESTION

Calculate the probability and expected monetary value (EMV) of path A–C of the figure below.

image

ANSWER

Probability=(.50)(.20)=10%EMV=(.50)(.20)($100,000)=$10,000

[Planning]

7 QUESTION

How is the risk impact scale used?

ANSWER

To identify the severity of each risk’s effect on the project objectives.

[Planning]

8 QUESTION

A project has a 50 percent chance of making a $10,000 profit and a 20 percent chance of losing $50,000. What is the EMV of the project?

ANSWER

EMV=(.50)($10,000)+(.20)($50,000)=$5,000

[Planning]

9 QUESTION

What are triggers? What other term can be used to define them? Provide an example.

ANSWER

An indication or warning sign that a risk has occurred or is about to occur.

Risk symptom.

Failure to meet intermediate milestones may be an early warning signal of an impending schedule delay.

[Planning]

10 QUESTION

What is risk mitigation?

ANSWER

A risk response strategy is where the project team acts to reduce the probability of occurrence or impact if the risk. Taking early action to reduce the probability and/or impact of a risk occurring on the project is often more effective than trying to repair the damage after the risk has occurred.

It is a tool and technique in plan risk responses.

[Planning]

11 QUESTION

What is the purpose of a risk management plan? List five of the ten areas it should include.

ANSWER

To describe to all stakeholders how risk management will be addressed and performed on the project.

Methodology; roles and responsibilities; budgeting; timing; risk categories; definitions of risk probability and impact; probability and impact matrix; revised stakeholder tolerances; reporting formats; and tracking.

[Planning]

12 QUESTION

How can earned value be used in control risks?

ANSWER

To monitor overall project performance by indicating potential deviation of the project at completion from cost and schedule targets. Deviation may indicate the potential impact of threats or opportunities.

[Monitoring and Controlling]

13 QUESTION

What is risk appetite?

ANSWER

The degree of uncertainty an entity is willing to take on in anticipation of a reward.

[Planning]

14 QUESTION

What is the purpose of reserve analysis?

ANSWER

To compare contingency reserves remaining against risk remaining in order to determine if the remaining reserve is adequate.

[Monitoring and Controlling]

15 QUESTION

Describe the output from identify risks.

ANSWER

Risk register, which will now include the following initial entries:

  • List of identified risks
  • List of potential responses

[Planning]

16 QUESTION

What is statistical independence?

ANSWER

The independence of two events in which the occurrence of one is not related to the occurrence of the other.

[Planning]

17 QUESTION

When is a contingent response strategy used?

ANSWER

Only when certain, previously identified, events occur. Events that trigger the contingency response should be defined and tracked.

[Planning]

18 QUESTION

What are four ways to deflect or transfer a risk?

ANSWER

  • Purchase insurance or a performance bond
  • Use a warranty
  • Use a guarantee
  • Use a subcontractor

[Planning]

19 QUESTION

What is risk acceptance?

ANSWER

Acknowledging a risk but taking no action to avoid, transfer, or mitigate it. Acceptance can be active (for example, preparing a contingency plan) or passive (that is, dealing with the risk if and when it occurs). The risk may be a threat or an opportunity.

[Planning]

20 QUESTION

How are checklists used in risk identification? Provide one advantage and one disadvantage of using a checklist.

ANSWER

To itemize all types of possible risk to the project.

Advantage: Quick and simple.

Disadvantage: Impossible to build an exhaustive checklist.

[Planning]

21 QUESTION

What are four strategies for dealing with opportunities?

ANSWER

  • Exploit
  • Share
  • Enhance
  • Accept

[Planning]

22 QUESTION

During which process are risks prioritized for further analysis or action by assessing and combining their probability of occurrence and impact?

ANSWER

Perform qualitative risk analysis.

[Planning]

23 QUESTION

What are risk consequences?

ANSWER

The effect on project objectives if the risk event occurs.

[Planning]

24 QUESTION

At which phase(s) in the project life cycle is significant risk thought to have the greatest impact?

ANSWER

Project Execution and Closeout (Termination).

[Planning]

25 QUESTION

In the following figure, what is the probability that Milestone B will be completed according to schedule, given that activities 1, 2, and 3 each have a 90 percent probability of completion according to schedule?

image

ANSWER

Probability=(.90)(.90)(.90)=73%

[Planning]

26 QUESTION

What types of enterprise environmental factors are inputs to identify risks?

ANSWER

  • Commercial databases
  • Academic studies
  • Published checklists
  • Benchmarking
  • Industry studies
  • Risk attitudes

[Planning]

27 QUESTION

What is a project risk?

ANSWER

An uncertain event that, if it occurs, has a positive or negative effect on at least one project objective, such as time, cost, scope, or quality.

[Planning]

28 QUESTION

What is the difference between a risk and a problem?

ANSWER

A risk is a future phenomenon (or event); it has not yet occurred. A problem, on the other hand, currently exists. Problems are often called issues.

[Planning]

29 QUESTION

What should you do to avoid a risk?

ANSWER

Adopt an alternative strategy—find another approach to get the job done, which entails changing the project management plan.

[Planning]

30 QUESTION

When should a risk urgency assessment be performed? What are four indicators of priority?

ANSWER

During perform qualitative risk analysis

  • Probability of detecting the risk
  • Time to effect a risk response
  • Symptoms and warning signs
  • Risk rating

[Planning]

31 QUESTION

How are contingency reserves calculated?

ANSWER

Based on the quantitative analysis of the project and the organization’s risk thresholds.

[Planning]

32 QUESTION

What is a risk premium?

ANSWER

Money paid to transfer the risk to a third party.

[Planning]

33 QUESTION

What is the responsibility of the risk response owner in the control risks process?

ANSWER

To periodically report to the project manager—

  • The effectiveness of the risk plan
  • Unanticipated effects of the risk under observation
  • Any corrective action taken

[Monitoring and Controlling]

34 QUESTION

This figure presents results obtained using what technique?

image

ANSWER

Monte Carlo simulation of a project schedule.

[Planning]

35 QUESTION

What is a risk breakdown structure?

ANSWER

A hierarchical depiction of all identified project risks structured by risk category and subcategory that pinpoints the areas and causes of potential risk. It is one of several techniques used in risk management plan.

[Planning]

36 QUESTION

What are four updates from the perform qualitative risk analysis process?

ANSWER

  • Assessments of probability and impacts for each risk
  • Risk ranking or scores
  • Risk urgency information or risk categorization
  • Watch list for low probability risks or risks requiring further action

[Planning]

37 QUESTION

What is used as a model for simulation for a cost risk analysis?

ANSWER

Cost estimates

[Planning]

38 QUESTION

Risk attitudes of the organization and stakeholders can be influenced by three factors, name them.

ANSWER

  • Risk appetite
  • Risk tolerance
  • Risk threshold

[Planning]

39 QUESTION

Who should attend a meeting to develop the risk management plan?

ANSWER

  • Project manager
  • Selected project team members
  • Anyone in the organization responsible for managing the risk planning and execution activities
  • Stakeholders

[Planning]

40 QUESTION

This figure represents what risk quantification technique?

image

ANSWER

Decision-tree analysis.

[Planning]

41 QUESTION

When should you avoid a risk? Provide four examples of avoidance.

ANSWER

  • When you want to eliminate it.

Examples include:

  • Extending the schedule
  • Changing the strategy
  • Reducing scope
  • Shutting down the project entirely

[Planning]

42 QUESTION

What is the output of the perform quantitative risk analysis process?

ANSWER

Project documents updates

[Planning]

43 QUESTION

How is expected monetary value computed?

ANSWER

Expected monetary value is the product of two numbers: risk event probability (an estimate of the probability that a given risk event will occur) and risk event value (an estimate of the gain or loss that will be incurred if the risk does occur).

[Planning]

44 QUESTION

What does a continuous probability distribution represent? What are two examples?

ANSWER

The uncertainty in values, such as durations of schedule activities and costs of project components.

Beta and triangular distributions.

[Planning]

45 QUESTION

What are three categories of risk?

ANSWER

  • Sources of risk
  • The area of the project affected
  • Common root causes

[Planning]

46 QUESTION

When should identify risks be performed?

ANSWER

Identify risks is not a one-time event; it should be performed on a regular basis throughout the project.

[Planning]

47 QUESTION

What is a decision tree? How is it used in perform quantitative risk analysis?

ANSWER

A diagram that shows a decision that is being considered and the implications of choosing one or more available alternatives. The branches of the tree represent either decisions (shown as boxes) or chance events (shown as circles).

Used to compute expected monetary values for each branch of the tree to help the project team quantify each decision alternative.

[Planning]

48 QUESTION

What is a sensitivity analysis? What is a typical display of a sensitivity analysis?

ANSWER

A method used to determine which risks have the greatest potential impact on the project.

Tornado diagram.

[Planning]

49 QUESTION

Electing to use older technology rather than buying the latest device represents what type of risk response?

ANSWER

Avoidance.

[Planning]

50 QUESTION

How are schedule simulation results used?

ANSWER

To quantify the risk of various schedule alternatives, different project strategies, different paths through the network, or individual activities.

[Planning]

51 QUESTION

List the six processes in project risk management?

ANSWER

  • Plan risk management
  • Identify risks
  • Perform qualitative risk analysis
  • Perform quantitative risk analysis
  • Plan risk responses
  • Control risks

[Planning and Monitoring and Controlling]

52 QUESTION

What are residual risks?

ANSWER

A risk that remains after responses have been implemented.

[Planning]

53 QUESTION

What are secondary risks?

ANSWER

Risks that arise after implementing a risk response

[Planning]

54 QUESTION

What is the most common active risk acceptance strategy?

ANSWER

Establishing a contingency reserve, to include amounts of time, money, or resources, to handle the risks, should they occur.

[Planning]

55 QUESTION

What is the purpose of risk audits? When are they performed?

ANSWER

To assess the effectiveness of the project’s risk management process and to examine and document the effectiveness of planned or unplanned risk responses in dealing with risk occurrences.

Throughout the project life cycle.

[Monitoring and Controlling]

56 QUESTION

For what category of risk would you use the “exploit” strategy?

ANSWER

For positive risks or opportunities.

[Planning]

57 QUESTION

What is a SWOT analysis? How is it used?

ANSWER

A strengths, weaknesses, opportunities, and threats analysis.

Used in identify risks, it tends to increase the number of project risks considered.

[Planning]

58 QUESTION

What is an assumptions analysis? How is it used?

ANSWER

An examination of the validity of assumptions as they apply to the project.

Used in identify risks to identify risks by examining the inaccuracy, inconsistency, or instability or incompleteness of assumptions. Assumptions are tested during perform qualitative risk analysis.

[Planning]

59 QUESTION

What action should the project manager take to ensure that each risk response is implemented and monitored?

ANSWER

Identify and assign an individual to own each risk who will take personal responsibility for protecting the project objectives from the risk’s impact.

[Planning]

60 QUESTION

What are three examples of risk diagramming techniques?

ANSWER

  • Cause-and-effect diagrams
  • Systems or process flowcharts
  • Influence diagrams

[Planning]

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset