ANNEX A1

MANAGING CLAIMS IN CONSTRUCTION

A claim is a demand for something due or believed to be due, usually as a result of a change in basis in the project execution; a variation or deviation in risk allocation; an action, direction, or requested change order against the agreed-upon terms and conditions of a contract or a part of the construction, which has failed or is not performing properly and cannot be economically resolved between the parties. Claims can also arise due to contract omissions, unclear language, and consequential misinterpretations. In construction, the demand is usually made for additional compensation for work deemed to be outside of the contract, or an extension to the completion time, or both. There are a number of situations for claims to take place and these should be viewed from two perspectives: the party making the claim and the one defending against it. However, the distinction between a claim and a change is the element of disagreement between the parties as to what is due. If agreement is reached, the claim transitions to an approved change request or, as more commonly referred to in construction, an approved change order, which modifies the contract. In the absence of an agreement, the claim may proceed to formal negotiation, mediation, arbitration, or litigation before it is resolved.

Litigation in most countries is the worst alternative, followed closely by arbitration, but may be the only way in which a claim can be resolved. It is far better to resolve the claim situation, even if the proposed resolution is not the most advantageous to the disputing parties, than to hope for a more favorable judgment through litigation. Often, claims are thought of in terms of a contractor making claims against an owner or other prime party and by subcontractors against a contractor, but claims can also originate with an owner who believes that a contract requirement is not being met or completed on time or in some form has caused undue damages to the stakeholder. Unresolved issues can escalate into a claim and ultimately a dispute among the contractual stakeholders.

Although agreed-upon changes to the contract documents occur frequently, disputes among the stakeholders of a project also occur frequently, so the contract should include clauses to prevent claims and to manage and mitigate their effects. Special attention should be paid to the management of project agreements in order to mitigate potential disputes that could arise. An international project involving parties from different countries raises the possibility of claims and it is necessary to establish, very early, the legal conventions and common rules for a good working relationship. Claims management describes the processes required to prevent claims, to mitigate the effects of those that do occur, and to manage claims quickly and effectively. This annex presents an outline for claims management, including appropriate dispute resolution methods. It is intended to stimulate a careful approach to contract preparation, contract management, project documentation, and expeditious resolution of claims, when applicable.

A1.1Claims Management in the Construction Industry

Generally, a construction claim is not necessarily a negative endeavor and does not necessarily reflect a bad project; it is the administrative process in which to settle a financial or cost disagreement and sometimes involves the contractual time for completion. When a buyer and seller cannot reach an agreement on compensation or cannot agree that a change has occurred, a contractual dispute may result, which may have a negative impact on the project and the relationship of its participants. Nowhere else is the motto “time is money” more prevalent than in the construction industry.

A1.1.1The Construction Environment Is Complex

Practically all project work performed involves an agreement or contract among the organizational participants. The organizational influences and project life cycles are a testament to the integration complexity. For example, the integrative nature of these projects is understood by a new roadway that disrupts exiting traffic flow, crosses existing infrastructure, passes through the natural environment, requires the acquisition of property, and even forces the relocation of communities. Consider the thousands of components that make up a finished tower, the transition between these materials, and the fact that they all are procured through written contract documents. To a further extent, construction may involve the unforeseen elements encountered when constructing a marine harbor, dredging waterways, or tunneling through mountains or beneath existing infrastructures. All of these elements dictate the scope of a project that is initiated in response to the needs and requirements of the stakeholders. It is for this reason that special attention should be paid to the management of those agreements in order to mitigate any potential disputes that may arise.

A1.1.2 Claim Prevention as a Priority

Construction activities are generally carried out in complex, highly sensitive, and changing environments. Perfect conditions and control are nearly impossible to obtain. Clearly, the best way to prevent claims is to eliminate the unknown areas to maximize what is known, and resolve changes to avoid potential disputes. Thus, the emphasis is on keeping issues in focus, prioritized, and resolved and to prevent them from becoming claims. Construction project management processes and properly documented outputs of these processes help considerably toward mitigation of a majority of possible claims. Further, research has shown that contracts based on sound and proven principles, internationally established contract guidance documents, and formalized construction project management methodologies lead to a considerable reduction in claims. A defined mechanism for claim resolution should be present in the contract agreement along with prioritization for resolution.

Having a well-developed plan is critical—one that provides for flexible implementation consistent with the plan as well as thorough communications with all stakeholders. Lack of follow-through, random changes to performance or schedule, unknown conditions, resource problems, and slow decision making are all factors that can negatively affect the project. Early recognition of potential problems, and open communications regarding possible alternatives or changes to the plan create a collaborative environment in which claims are less likely to occur.

Being proactive, such as keeping project documents in order, traceable, and retrievable in a timely manner, is a sound approach toward claims prevention and is the least invasive and least costly route in resolving potential claims and contract disputes. The practices described in this annex can mitigate and often eliminate the occurrence of claims.

A1.2 Claims Management Planning

The rise of a claim, its documentation, and its development by a plaintiff can be very expensive. Similarly, the defense of the claim can be equally expensive and both are without any guarantees of a favorable outcome. Therefore, from the stakeholder's perspective, the goal for claims management is to prevent claims entirely and, if not, to resolve them at the earliest opportunity for the least cost and least disruption to the project. To do so, one should first be able to recognize potential claim situations, either contractual or performance-based. Recognizing potential claim situations starts with sufficient knowledge of the project scope and contract requirements. This awareness helps identify the potential risk that may arise with changes in scope or a potential modification to the contract. The environment of potential claims begins with the planning processes, not only in the Project Procurement Management Knowledge Area but also in Project Risk Management, Project Stakeholder Management, and Project Communications Management. These influences form the basis for an agreement between parties as the seller and buyer. The interpretation of the contract documents from a legal perspective is beyond the scope of this Construction Extension but is a necessary requirement for contractual stakeholders. In-house or retained professional resources skilled in law and legislation are common in design and construction. Outputs, particularly from the planning processes, may prove invaluable to the legal professionals if and when their services are needed.

Having a thorough project management plan is a fundamental component and the most important factor in claim prevention. A clear and carefully described scope of work, a reasonable schedule, an appropriate method of project execution tailored to the type of project, and an acceptable degree of risk involved contribute to the elimination of claims. An assessment of the construction works encompassing all requirements of the project plan should be satisfied in conjunction with the major stakeholders to the project plan. Up-front partnering and team-collaboration opportunities are techniques that build consensus and collaboration among the team members. These techniques help reduce the perception of distrust and improve the interfaces that may have an effect on timely decisions, both at the site and at administrative levels.

A well-written contract with fair contract terms provides a basis for minimizing claims when it comes to scope changes and unknown site conditions, force majeure delays and fortuitous events, and timely reporting and fair-notice provisions. Having a detailed review of the dispute resolution clauses before addressing a dispute can help alleviate uncertainty and ambiguity on these matters and keep the dispute from escalating to a full claim. Legal advisors may also be called upon to help interpret contractual language that may be ambiguous.

Claims can be minimized by the use of a risk management plan that allocates the risk between the parties on the basis of which one has the most control over the risk factor involved. Unfairly shifting the maximum amount of risk and the ability to control that risk to a contractor is an invitation to claims. The up-front understanding of regular schedule updates and incorporating delay activities as agreed between the owner and the contractor contributes significant importance in addressing time impacts. Project Integration Management addresses change control along with the generally recognized good practices for managing changes. In addition, construction changes and the perception of a change or changed condition require an effective strategy to avoid hard lined positions, which only serve to escalate a claim situation. The change control process should designate levels of authority for the decision-making process, and for incorporating all efforts to eliminate or reduce the potential for a dispute.

A1.2.1 Planning Activities for Claim Prevention

All contract documents should be written in clear, unambiguous terms. Pre-tender meetings between stakeholders prior to contract finalization help to clarify the details, requirements, and expectations for the project. Declarations from the contracting parties regarding bid quantities can also prevent claims arising from project scope. Further, requirements for cost, schedule, scope, and specifications should be clearly stated, reasonable to accomplish, and mutually agreed upon by stakeholders. Effective and qualitative reviews by all parties increase clarity around the schedule, planned work, progress, and as-built project documentation.

The use of a constructability review can avoid field errors and unnecessary changes in construction methods, all of which can lead to claims. This review, along with effective procedures for additional qualifications and clarifications, is vitally important. The request for information (RFI) procedure is a common component for clarifying the intent, design details, or instructions for the construction contractor.

Contracts requiring designer and owner approval for shop drawings, materials for construction, RFI responses, and similar documents should contain a clause that states a reasonable time frame for a response to be given. If this deadline is not met, the contractor may unintentionally be impacted and may have grounds for a claim for extra contract time and/or added costs. The general and special conditions along with project performance reporting requirements describe other process and system tools that contribute to effective communication and reporting on project progress, events, and administrative processes, such as change order logs, change order proposals, submittal tracking, and progress meetings. Many, if not all, of these project documents and tools may be associated with a future claim; thus, prescribing clear expectations of their use can help with documenting factual circumstances and conditions.

Prequalification of designers and contractors has the benefit of dealing with experienced and qualified organizations that are less likely to enter into a wishful contractual relationship to pursue claims, thus reducing or avoiding the risk of a situation that could quickly and frequently be driven to frantic claim activity. These organizations usually have a higher standard of professional conduct and one in which the focus is on resolving situations that lead to claims. Several of the contract delivery methods are geared specifically for this purpose.

A1.2.2 Project Partnering

Projects that use a project team collaboration technique for project-specific partnering are often less susceptible to claims because of the mutual dedication and commitment that partnering promotes. Processes and systems can be established that lead to better communication, timely turnaround of submittals, prompt decision making, and often a practical form of issue escalation when a potential situation is discovered. Partnering can be a contract requirement; however, it is most often an optional provision for the contractor and the owner. Partnering strives to optimize the written and unwritten commitments of the stakeholders to reach an early understanding of how to conduct business professionally and within a code of conduct, thus making committed efforts toward project success (see also Figure A1-1). This technique is considered an alignment of the project management Knowledge Areas and relationships among the primary stakeholders. The following are some of the beneficial drivers for an effective partnering relationship:

  • Setting high standards for the project team,
  • Advocating continuous partnering efforts through project completion,
  • Active and persistent participation in the partnering objectives and processes,
  • Improving management processes and systems,
  • Keeping communications project-focused, and
  • Maintaining the principles and effective habits of alignment.

Good practices and sound business habits of partnering are vital to its success. The following may be considered components of the partnering team's business plan:

  • Focus and forecasting. Focus on “what” has to happen to deem a project successful. This may require forecasting potential risks and opportunities, along with appropriate action plans.
  • Systems and processes. Adjust and monitor new or existing business and technical administrative processes to improve systems, response times, and communication efforts.
  • Professionalism. Emphasize professional conduct and behaviors; demonstrate just and fair practices; create a positive, proactive culture; and control tension-reaction situations.
  • Resolutions and confrontation. Establish a framework and proactive processes for evaluating project issues in order to avoid a dispute that could jeopardize the partnering foundation. Create an issue elevation and resolution system involving the executive or sponsor participants or utilizing an independent neutral to assist in reaching resolutions.
  • Leadership, roles, and authority. Clearly define the various roles and responsibilities of project participants, especially the “go-to” individuals. Establish change order approval levels and decision-making authority. Lead by consistently demonstrating and acknowledging teamwork, project accomplishments, and team resolutions.
  • Feedback. Do not wait until project completion to see how well things went. Instead, periodically measure the partnering efforts, provide opportunities for everyone to respond, take action where needed, and continually seek to improve from lessons learned. See also Figure 4-2 that illustrates a form of team effectiveness.
  • Partnering teams and expansion. Hold regular core management team (CMT) partnering meetings. Provide an environment conducive for the field, administrative, and line-level teams to practice partnering. In time, these teams may be expanded to expose more individuals to the partnering efforts.
  • Routine and consistent engagement of management. Conduct routine and consistent engagement of members of senior management who are responsible for dispute resolution and the overall team working relationships. The executive or sponsor team should not be allowed to slide by; rather, hold them accountable for supporting the partnering efforts and seek their advice. Advise other direct stakeholders that you are partnering.

images

A1.2.3 Specific Claim Litigation Prevention Techniques

The construction industry has made great progress in creating proactive alternative techniques for resolving claims and contractual disputes. It should be noted that contracts often stipulate a minimum period for amicable resolution between the parties as a prerequisite to the formal litigation process. Some of the more prevalent techniques that can be used during the project and prior to claim litigation include:

  • Dispute resolution board (DRB). Projects that are large and complex can establish a DRB at the outset of the project. The DRB is comprised of a panel of independent neutrals that do not have a financial or business relationship with the stakeholders of a project. The DRB serves in an advisory role to the contractual parties by attending regular progress meetings and offering suggestions and comments, not only on normal operations but also on potential claim situations. In other formats, the DRB can act as an arbitration panel over any disputes that arise during the project so that potential claims are turned into changes or are dismissed for good reason before the project closes.
  • Independent neutral. On small or moderately sized projects, stakeholders can opt to share jointly in the cost of an independent neutral who can act as a technical or construction advisor to the stakeholders and project management team. This neutral party, sometimes referred to as an independent project advisor (IPA), can analyze the situation and provide recommendations for fair resolutions, including time and cost impact assessments. In addition, this individual can offer expert advice in terms of project management processes and practices where project teams are encountering difficulty and conflict. On larger projects, multiple independent neutrals may form an advisory team to help interpret technical problems, suggest alternatives, and provide advice for problem solving and decision making on change requests.
  • Intervention partnering. Similar to the independent neutral, a partnering facilitator who is skilled in disputes and mediation can be brought in to facilitate the resolution of pending claims. This can also be used as an alternative dispute resolution process. This process involves bringing in other independent experts to assess the project, evaluate the claims, and assist the stakeholders in effectively completing the project and further mitigating consequential impacts and project delays.
  • Mediation. While this is most often implemented at the close of a project when claims are outstanding, nothing precludes the use of mediation techniques during the project. Often, mediation is one of the first alternatives to litigation and is an effort made by stakeholders to achieve an equitable settlement with the help of skilled professionals.

A1.2.4 Joint Recognition of Changes and Documentation

The preferred practice for reducing potential claims is for the parties to recognize that a change has occurred and that both parties are realistic in assessing the potential cost and time impacts. A clear change order process should be implemented and incorporated in the contract to manage both in-scope and out-of-scope changes. This change process requires timely and appropriate documentation that can lead to quick acknowledgment of a change. Poor, untimely, or inadequate documentation will only prolong an argument between the parties. Good documentation is also a primary component for defense of claims. The tools and techniques for performance reporting are effective mechanisms that lead to good documentation and factual analysis, which are essential to timely and successful claim resolution. It matters that the intention of either party is not to damage the other party, which only leads to further negative impacts on project completion and costs. Also, the project management information systems, configuration management, change management, and work authorization systems, which collect and distribute information, all contribute to the recognition and documentation of changes and change requests.

The facts and truthfulness in data collection and reporting are important. With current and emerging technologies (e.g., building information modeling [BIM], dashboards, photo and video, and immense data storage capacity and retrieval), the capability to share and exchange factual project data is almost limitless. The results of effective and timely claim prevention yield approved change requests for compensation or requests for extensions of time, or both, which eliminates claims. Disputes and fighting through litigation are not in the best interest of either party. Stakeholders who have successfully prevented or resolved potential claims, without the added time and expense of experts and attorneys, generally develop an appreciation for trusted relationships and a respect for one another. This, in turn, can lead to future collaborative working relationships and projects.

A1.3 Claims Management Monitoring and Control

It is rare that a stakeholder plans for a claim or contract dispute. For the most part, stakeholders are optimistic toward their contracts and seek to avoid claim situations. In the event that a claim situation arises, the stakeholder should be prepared to identify the situation in a timely manner and be forthright in its evaluation to determine if the potential claim is justified. Owners should require a project management plan that details systems, policies, processes, procedures, and documentation. Such a procedure, if followed diligently, makes document processing effective and efficient and has proven to mitigate delays and decrease disputes and subsequent claims.

A1.3.1 Claims Identification and Initial Justification

Many claims are the result of an unresolved request for a change order, conflicting contract document interpretation, or changed or unknown conditions. A contract that is not administered in a timely manner causes time and cost impacts on the project. Project performance is another area where claims may arise due to either the quality of work performed or the progress of the work not being obtained to meet the contract completion date.

Regardless of the origin of the potential claim, the claims identification process should start with a clearly understood project scope and contract and include a written description of the claim, time and cost impacts, prompt payments, capability gap analysis, expert judgment, documentation, pending claim file, and statement of claim as follows:

  • Project scope and contract. The scope of work outlined in the contract includes all plans, specifications, referenced codes, industry standard publications, regulations, and jurisdictional laws. The contract generally includes the terms and conditions that apply to the work, provisions relating to changes, changed conditions, appropriate notice requirements, and administration. Strict adherence to the contract can be very difficult if one does not fully understand its requirements. However, a strict or difficult to follow contact does not excuse noncompliance. Seeking legal counsel or expert judgment to assist with the interpretation and requirements is proactive and time well spent. The contract consists of the provisions relating to changes and notice provisions. In many cases, claims not made in a timely manner could become invalid.
  • Description of claim. This is a written description of the work believed to be outside of the contract, where it occurred, and when it took place, including contract specification references that support the requested claim. A justification statement describing the basis for the claim and referencing the contract section that supports the contention should be included. The claim should document the activities that were affected by the situation, including the resources that may have been impacted, and address the project schedule and any additional contract time required to perform extra work. Contemporaneous documentation should be recorded promptly at the time of the occurrence and cover all aspects that support the claim and the contract provisions.
  • Time and cost impacts. Should the claim impact the contract time, a record of when the alleged extra work commenced or will commence, and when it ended or is estimated to end, should be documented. The current project schedule baseline becomes one of the primary project documents/records, which demonstrates the impact on the project. Time extension claims that result from delays to the work due to events such as unusual weather, strikes, or other force majeure items outside of the contractor's control may be valid, although they might not be compensable. All time extension requests and time impact analyses should be reviewed promptly in order to avoid claims later of constructive acceleration. Constructive acceleration is generally defined as compelling a contractor to complete its work on time despite legitimate, documented requests for time extensions. This type of claim most frequently occurs when owners ignore time extension requests, deny them outright without respectful analysis, or refuse to engage with contractors over such requests, resulting in substantiated cost impacts for the contractor. When these delay claims are not dealt with in an effective manner, the working relationship is impacted in a negative manner.

    The owner team should have the ability to analyze and resolve delay claims. Likewise, owners should ensure that their project staff deals with the time extension requests promptly, objectively, and in accordance with the terms and conditions of the contract. Cost impacts are the most common type of claim involving the payment or lack thereof for claimed extra work or changed conditions that made the work more difficult and costly to perform. Accuracy in time reporting and documenting the actual changed condition with supporting documentation is a key to identifying and justifying the claim.

    An initial quantification of the value of cost damages should be made. To further elaborate, the types of time impacts are often described as critical/noncritical delays, excusable/nonexcusable delays, compensable/noncompensable delays, and concurrent delays. Sellers should comprehend these types of delays and buyers should recognize the differences so as to augment the discussions and better understand delay consequences in relation to the overall project timelines.

    Analyzing time and cost overruns often requires a technical forensic analysis that can withstand formal dispute resolution forums, such as litigation or arbitration. Generally, forensic analysis specialists are brought in for several reasons: the need to choose a methodology and develop a forensic schedule analysis that will stand up under scrutiny, the need to provide an objective expert opinion, and the need to support negotiations.

  • Prompt payments. Construction is mostly done on a cost-reimbursable basis: the contractor finances the construction of previously agreed-upon parts of the project and is paid when parts of the work are accepted. Depending upon the contract terms, contractors may be able to seek routine reimbursements for work successfully completed during the previous period. Project owners (especially public owners) should establish systems for the prompt handling of contractor payment requests in order to prevent late or slow payments. A failure to do so may subject owners to legal penalties or slow payments, which may adversely impact a contractor's financial ability to proceed with the work as planned and leave the owner exposed to claims of owner interference with the work. Many public work projects are subject to statutory prompt pay provisions, and owners, design professionals, and contractors should be conversant with them.
  • Capability gap analysis. Schedule review, delay analysis, and time extension issues, especially on large, complex construction projects, can be difficult to interpret. If the owner's project team does not have the capability to review CPM schedules, time extension requests, and delay claims, the owner should engage a professional to perform these functions. If both the owner and the contractor teams have competent, professional construction project managers with a mutual understanding of the contract requirements, it is more likely that time extension requests and delay claims can be resolved on the job site through negotiation. Thus, the likelihood of time-related disputes could considerably decrease.
  • Expert judgment. Depending on the project delivery method employed, the owner may seek advice from one or more of the contract stakeholders as to whether a claim is valid. This may be the designer of record or the construction manager. Seeking the advice of outside legal counsel is also suggested. It is often worthwhile to reach a consensus among several people as to whether or not the situation in question merits claim status. In some situations, such as with potentially expensive or technically challenging claims, legal advisors and/or construction consultants experienced with claims may be consulted for expert opinions.
  • Documentation. One of the most important factors in the claim process is the need for proper, timely, and thorough supporting documentation, such as photographs and videos of the work in question, relevant contract sections and drawings, and narrative statements of persons involved in or associated with the work that is being claimed. Any correspondence, instructions, approved design details, or shop drawings related to the claim are also considered to be supporting documents. In addition, as-built schedule information for the time and work days for performance of the claim should be noted. Moreover, the contract documents may require separate cost accounting for claimed extra work. See also Section 10.2.1 for generally recognized acceptable practices for project documentation.
  • Pending claim file and statement of claim. As a good practice, items identified as potential claims should be kept in their own separate files that contain all related documentation, including correspondence and contract references. This ensures that relevant information and documents are collected and retained in an accessible file or database. Without this proactive approach for organizing and indexing, managing the hundreds to tens of thousands of project documents will become an extremely expensive component of qualifying and proving the claim. Based on the circumstances surrounding the potential claim and through an initial claim analysis, a statement of claim can be prepared in accordance with the process and procedures set forth by the contract.

A1.3.2 Claims Quantification

Once an issue has been reviewed and internally justified to have merit as a potential claim, a decision should be made to determine if a claim is truly worthy of pursuit. An adequate assessment should be made of the possible stakeholder consequences, positive and negative, when a claim is to be submitted. The next step is to quantify the potential claim in terms of additional compensation, a time extension to the contract completion, or both. Claims often tend to create barriers for prompt resolution due to the differences in the cost and time impact perspectives between the stakeholders. Nevertheless, there are proper and logical ways of determining the cost of the extra activity, added work, or consequential damages in terms of time and money. The process is best served by using a cause-and-effect approach that specifically identifies the cause, the circumstances surrounding it, and its effect on the specific work item and possibly other items that have been indirectly affected. Certain claims can have an effect on other aspects of the construction project, making such works more costly and causing disruption to work sequencing or delaying activities. To the extent that these indirect effects can be justified and quantified, they are part of the total impact of the claim.

The statement of claim forms the foundation for further analysis and quantification. First, a specific component of the contract prescribes cost items that can or cannot be claimed by means of a thorough contract and legal counsel review. Jurisdictional or international laws regarding reimbursement may also affect the claim elements related to cost reimbursement. Second, project time and cost records should be analyzed for factual and substantiated documentation. Careful control and management of project documents cannot be overemphasized should a claim be destined for remedy via a judicial court system. All stakeholder documents and records, including corporation records, may be discoverable through the court of law. The additional effect on or consequence of the balance of the contract work caused by the claimed activity should be treated in the same manner as data collected for the claimed activity itself. Careful and explicit documentation should be maintained to fully support these types of activity impacts, including the use of the project schedule to demonstrate the claim impact. Contemporaneous documentation far outweighs documents created after the fact. With the increasing use of new technology, the ability to capture and index real-time data should not only make substantiating the claim more efficient, but also serve to more quickly disprove or support alleged claims.

Documentation should include the following information:

  • Quantity measurement. Actual quantities of the claimed work are measured in terms of cubic meters of concrete or earth, weight of steel, or linear measures of piping and units of electrical work. When disagreements arise, agreement of the specified quantity is one of the first aspects to review. In addition to material quantification, detailed activity cost tracking can document all resource (labor and equipment) hours expended on the claimed item. Actual labor hours can be quantified for the extra work or for the disruption of other activities. It is important that this quantification be accurately performed and treated as a separate line item in the cost reporting mechanisms. With effective labor tracking, the quantification of extra work hours is straightforward and is a far more effective and credible method for substantiating actual costs than an after-the-fact, subjective description or estimation of labor. Further, not all extra work can be quantified by unit weight or measure, so the difficulty or complexity of work performance is best documented by a time and material process.
  • Cost quantification. Cost quantification covers the cost of the labor, material, and equipment involved in the claimed work and may involve estimation. Cost records, where available, provide the basis of the actual cost. If not, the cost is estimated using current applicable rates. Additions for overhead and profit are common and usually proper and should be considered part of the change.

    The home office overhead (HOOH) is an indirect cost due to a project delay and is one of the more difficult impact costs to demonstrate and justify. Judicial courts have gone back and forth on this justifiable cost to the point that many buyers attempt to disallow it in the contract general and special conditions, but not always successfully. Sometimes the claimed work has an effect on other project work and home office operations that can result in additional cost. Usually, this cost is estimated, since the cause-and-effect relationship is not obvious. Often, though, the justification for this indirect cost is difficult to prove to the satisfaction of the opposing party. In some situations, given quantifiable work performance, a measured-mile-cost approach is used. In this comparative analysis approach, the actual costs and work efforts for a similar, unaffected work are recorded and used to determine the cost impact of disrupted and impacted work activities. In addition to direct project costs, the project owner can also be impacted by a delayed occupancy. The contractor could be affected by unavailability of contract labor and equipment resources to perform work on other projects, or by additional or extended general administrative costs to manage the project. Most contracts include a liquidated damages clause, should the project not be completed within the contract requirements. Although difficult to demonstrate and prove, the contractor can also be hurt by projects that limit its ability to perform other projects, current or prospective, and these damages are sometimes claimed as lost opportunity costs.

  • Schedule analysis. There are a number of schedule analysis techniques. Some of the available computer programs can help with this analysis but can also make it overcomplicated and can create illusionary effects. Forensic schedule analysis is a technical discipline distinctly separate from project planning and scheduling. Its methods can be manipulated and its understanding and practices go well beyond the skills of a common project scheduler. Considerations for the schedule analysis methodology include the timing of the analysis, whether it is prospective or retrospective, and whether its basic method is observational (interpretation/evaluation) or modeled (simulations with different scenarios). Further definition and description of these methods is beyond the scope of this extension, but this information is available from specific industry professions that offer detailed time-impact-analysis guides and practices. Expert schedule analysts are most often engaged to perform this type of work.

    One of the most common ways of assessing the schedule effect of changes and claims is to compare the as-planned schedule with the as-built schedule in order to support time extension requests. Other forensic schedule analysis techniques, several of which are commonly referred to as time impact analysis (TIA) techniques, each with its own advantages and disadvantages, include:

    • Impacted as-planned, what-if;
    • Collapsed as-built (sometimes called “but-for” analysis);
    • As-built analysis;
    • Contemporaneous period analysis (sometimes called a “window” analysis);
    • Contemporaneous detailed as-built;
    • Summary and fragment comparisons; and
    • As-planned vs. as-built.

    Since time management practices can vary widely, the preferred practice is to support the actual activity events with consistent schedule documentation through monitoring and controlling during project execution. The prevalence of daily diaries becomes a key component in substantiating work progress and delay disruption. The discussion of Project Schedule Management in Section 6 provides examples of schedule status and updating techniques. The effect on the critical path of the project schedule can be difficult to isolate because of all of the factors, often simultaneous, that affect construction schedules. Such delays to the project may be due to owner actions or inactions, such as late or partial access to work areas, information, or decisions. Further, when both parties cause delays, a separate analysis may be required for each case in order to properly allocate project delay responsibility. The Practice Standard for Scheduling [8] and CPM Scheduling for Construction: Best Practices and Guidelines [9] can serve to enhance the time management practices that are critical within the construction industry.

  • Contract law precedents. There are times when it is appropriate to seek legal advice. Relevant case law can also provide guidance as to what may or may not be included in the claim or how the claim may be evaluated in a court of law. Soliciting this expert judgment is a good practice and should be initiated before spending large sums of money to pursue a claim. It is noteworthy that the opinions from legal advisors and forensic experts are very different: attorneys tend to be advocates for the client, with no obligations to be objective, whereas forensic experts have obligations to provide objective, fair, and accurate analysis, which is more likely to prevail in dispute forums than subjective efforts to justify one side's position.
  • Fully documented claim. A complete claim document presents the quantification of the cost impact, the time extension request, and all supporting documentation. Usually, the contract outlines the submission procedures for claims. In certain government contracts, claims may need to be certified by a senior executive of the business who has authority to make such certification. This document can provide an outline of the claim, along with the specific costs that are being claimed. The claim document may become the working document that the opposing party uses to define its defense position or acquiesce to the claimed costs. The claim includes all direct costs or damages resulting from the claimed situation, including the supporting factors used in the cost and time calculation. Also, indirect costs are often quantified in a similar manner as the direct costs when justified by the effects of the claim on other aspects of the construction project. Proper data to support quantity calculations are required, including time records showing the extent of labor involved, equipment/machinery usage, wage rates, equipment rates, and invoices for materials that are included in the fully documented claim. Any time extension request should be fully described and presented in a form of schedule analysis.

A1.3.3 Claims Resolution

Even with a concerted effort to prevent claims, they still may occur. There may be an understandable disagreement as to whether or not the claim in question is a change to the contract, or whether the claimed amount of compensation or time requested is actual or perceived. When a claim situation arises to the point of a contract dispute, a step-by-step process is set in motion. Most all formal contracts contain a prescribed claim process that will dictate the method of resolution. It is axiomatic that the longer this process takes, the more expensive and disruptive it is to both parties. Therefore, the goal is to settle these issues quickly and at the lowest level of authority in the organization as practical. The process begins with negotiation, perhaps involving some level of senior management that has contractual and financial authority. Subsequently, the claim moves along to mediation, arbitration, or litigation, depending upon the remedies afforded by the contract. Alternative methods of resolution have been increasingly used because of the potential proliferation of claims and the expense of litigation. These alternative methods, referred to as alternative dispute resolution (ADR), may include mediation, arbitration, mini-trials, DRBs, or other global alternatives.

Examples of the method of resolution for a contract dispute are:

  • Expert judgment. Stakeholders and construction personnel are served well by seeking advice from experts in the area of construction claims. These professionals can often quickly assess the potential claim using the documentation and provide information regarding its validity, existing documentation to substantiate it, and an order of magnitude in terms of cost and effort to fully document and pursue the claim. These professionals often work directly with one party's attorney to combine both the technical and legal advice. The contract remains the ultimate baseline and means for resolution.
  • Negotiation. The first and best step to resolution is good faith negotiation. Any settlement is a good settlement when it comes to avoiding litigation. Even with a sound claim and legal justification, the litigation outcome in one's favor is not a sure thing. Sometimes the negotiation needs to be elevated to a higher level, but it still is a negotiation between parties trying to find an equitable solution.
  • Estimated cost of resolution. When the initial attempts at negotiation fail, it is prudent for each of the parties to estimate the cost of carrying the dispute further. Mediators are costly (but can be cost-effective) and some arbitration cases can approach the expense of litigation given the amount of discovery involved. An estimate of these costs can help in deciding the benefits of pursuing a claim. Sometimes the cost of pursuing or defending the claim can be considered a trade-off and used as part of the settlement funds to resolve the claim prior to litigation.
  • Claim assessments or expert reports. Professional construction consultants can be hired to assess the issue and, in some cases, provide an expert report outlining the cost, time, and business impact of the potential claim. The consequential time and cost impact on other activities as a result of the extra or delayed work is important information that should be evaluated in terms of potential recovery. Some assessments may reveal documentation discrepancies and problems self-inflicted by the stakeholder, which may prevent a full recovery. In some cases, an expert report may be obtained to corroborate the technical aspects of the claim.
  • Alternative dispute resolution (ADR). These methods are considered alternatives to litigation in a court of law and most often are far less costly:
    • Mediation is an effort by the stakeholders to achieve an equitable settlement by use of a skilled professional mediator.
    • Mini-trials and dispute resolution board (DRB) are part of a settlement process in which the parties present summarized versions of their respective cases to a panel of officials who have authority to settle the dispute. The process does not take place inside a courtroom, but rather it is held at one of the representing legal counsel offices.
    • Arbitration is just one step short of litigation and the judicial court system. This technique utilizes a trained professional or a panel of professionals (e.g., construction experts, attorneys, or ex-judges) to act as the judge and jury to listen to stakeholder arguments and testimony, assess factual and expert exhibits, and issue a judgment. International construction contracts by their nature have special conditions and specific treatments for this ADR. Most contracts will also prescribe adherence to the use of standard contract forms and the rules of arbitration governed by international courts.
  • Litigation. Litigation is the result when all previous attempts at settlement have failed. Construction lawsuits are commonly complex for juries to understand and often take a long time to present. Litigation is considered a last resort and is expensive in terms of cost and upset to the organizations involved. Parties entering into litigation should be sure that this is the only way the dispute can be resolved.
  • Equitable contract adjustment. Usually in the form of a change order or contract modification, an adjustment to the final contract amount is made as a result of the monetary settlement. The process of allocating this amount is usually an internal accounting function and varies depending on the type of public or private stakeholders involved. In cases where the contract cannot be closed because of a pending dispute, the contract can be closed upon resolution of the dispute.

Regardless of the prescribed resolution method, settlement should always be an option to the parties and they should remain open to this dialogue. There are many recorded legal cases in which the sellers and buyers have faced judgments that were not in their favor.

A1.3.4 Contract Law Interpretation

For sellers conducting business across international borders, an awareness of contract law precedents can be particularly important in learning how contract legal challenges may be decided. In a common law system, law is interpreted and thus “written” by judges hearing the cases. Decisions become the “rule of law” for all future cases that are factually similar. In civil or codified law, the law is written into statute or code books and is strictly interpreted by the courts of that country. Stakeholders involved in construction projects across international borders are encouraged to become familiar with these precedents or acquire the proper legal representation of that country.

A1.3.5 Bid Protests

The number of bid protests has been gradually increasing due to the increasing size of projects in the public sectors; the varying contract delivery methods; and perceived discrepancies, subjective evaluations, and sometimes unfair selection. Bid protests most often originate from the procurement side of public contracting. Some industry experts point to the ease in which a protest can be made due to changes in some government policies that allow protests for certain types of contract procurements. Protesting is one thing—winning a protest is another. Contractors invest large sums of money in preparing contract proposals. When agencies do not follow the procurement criteria or make arbitrary contractor selections, the promotion of fairness is challenged. However, other industry experts claim that protests can promote a form of voluntary corrective action by agencies in the public contracting arena.

A1.3.6 Ethics in Construction

It is unfortunate that unethical problems exist in both the corporate and operational levels within the construction industry. From falsifying quality control reports, to inappropriate labor mark-ups on direct cost contracts, to knowingly enforcing an unfair risk or site condition on a contractor, ethical issues in construction are an ever-present situation. Many organizations have created, adopted, and continue to use codes of ethics. However, having an ethics code does not necessarily mean that the organization's entire personnel and business practices uphold ethical standards. With the advent of more transparency between buyers and sellers through technology, ethical behavior can be improved; however, organizations should continue to focus on the factors within their control. The PMI Code of Ethics and Professional Conduct for project manager practitioners is a good place to start.

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset