PMI’s A Guide to the Project Management Body of Knowledge—Third Edition describes the Project Management Body of Knowledge as “the sum of knowledge within the profession of project management” that resides with practitioners and academics who apply and advance it. While the PMBOK® Guide—Third Edition provides a generic foundation for managing projects in the public and private sectors, this document addresses the specific practices found in public sector projects. This document supersedes the previous edition of the Government Extension, entitled Government Extension to the PMBOK® Guide—2000 Edition.
This extension to the PMBOK® Guide—Third Edition provides an overview of key attributes of project governance that apply to most public sector organizations and that are “generally recognized as good practice…applicable to most projects most of the time,” and with “widespread consensus about their value and usefulness.” It establishes a framework for ensuring effective and efficient management of projects in the public sector. It does not, however, provide practices or guidance that should be uniformly applied on all projects. The project management team is ultimately responsible for determining what is appropriate for any given project.
Readers should note that, while many of the references used in the Government Extension are derived from the PMBOK® Guide—Third Edition, its content is specifically designed to suit the unique characteristics of projects in the government sector. Project management professionals should plan to use both documents concurrently in the execution of their responsibilities. To that end, this chapter is organized into the following sections to reflect the structure of the PMBOK® Guide—Third Edition:
1.1 Purpose of the Government Extension
The PMBOK® Guide—Third Edition sets forth the subset of the Project Management Body of Knowledge that is generally recognized as good practice. It provides an overview of practices that apply to most projects most of the time, and for which there is widespread consensus about their value and usefulness. The concept of good practice implies that the correct application of skills, tools, and techniques not only can increase the chances of project success, but can be extended to many diverse application areas.
The Government Extension interprets and extends the precepts of proficient project management found in the PMBOK® Guide—Third Edition to public sector entities. The key characteristics of public sector projects are listed in Section 1.3 of this chapter.
Appendix D of the PMBOK® Guide—Third Edition describes application area extensions. Application area extensions are necessary when there are generally accepted knowledge and practices for a category of projects in one application area that are not generally accepted across the full range of project types in most application areas. Application areas reflect:
Projects undertaken by government organizations are primarily funded by and executed for the benefit of citizens, rather than for financial results. To this extent, the focus of the Government Extension to the PMBOK® Guide—Third Edition centers on two distinguishing factors peculiar to public sector organizations that can affect project governance:
This Government Extension provides a framework for improving the management of public sector projects. The recommendations presented here are focused on providing guidance in managing the intricacies of government project specifics. They provide guiding principles for ensuring the efficiency and effectiveness of project controls to allow accountability to a nation’s citizens, as required by public law.
1.1.1 Audience for the Government Extension to the PMBOK® Guide Third Edition
This extension serves as a foundational reference for anyone involved in or with the profession of project management, working for or doing business with public sector organizations. This includes, but is not limited to:
1.2 What Is a Project?
See Section 1.2 of the PMBOK® Guide—Third Edition.
1.2.1 Project Characteristics
See Section 1.2.1 of the PMBOK® Guide—Third Edition.
1.2.2 Projects vs. Operational Work
See Section 1.2.2 of the PMBOK® Guide—Third Edition.
1.2.3 Projects and Strategic Planning
See Section 1.2.3 of the PMBOK® Guide—Third Edition.
1.2.4 Why are Government Projects Unique?
Government projects are generally considered to have unique characteristics from those in the private sector. The project management team must recognize the following unique characteristics in order to manage the project efficiently and effectively:
1.3 Project Management in the Government Context
The PMBOK® Guide—Third Edition characterizes program management as “the centralized, coordinated management of a group of projects to achieve the program’s strategic objectives and benefits.” Their strong focus on strategic planning distinguishes such projects from more tactical projects.
In the private sector, projects are aligned with strategic plans and company objectives, and may be part of programs or portfolios. In large companies, such project hierarchies are formalized most of the time, whereas in small or mid-size organizations, the projects might only have implicit interdependencies.
1.3.1 Levels of Government
This extension applies to three generally recognized levels of government. What follows are representative descriptions of those levels that are widely recognized around the globe. It is not meant to be an exhaustive description of all levels of government worldwide.
1.3.2 Project and Stakeholder Interdependencies
Government projects are determined by the government’s agenda, and have to be approved and budgeted in advance. Government project are not normally analyzed on an individual basis; for larger bodies (such as national and regional governments), it is more practical to group them as programs from a budgeting and control perspective. The long approval and budgeting cycles require government projects to be much more strategically oriented than private sector ones.
In the public sector, not only is there a higher percentage of projects that are part of programs than in the private sector, but project interdependencies are more clearly identified and documented. The governance and management flows hierarchically from political agenda items down to the execution level (as represented by projects).
In most cases, the stakeholders involved at each level represent and draw authority from the stakeholders involved at the upper level in the hierarchy. For example, if a government agenda item requires cooperation at the program level from two agencies, the specific branches or divisions and stakeholders within each agency would be involved.
Indeed, the lower hierarchical levels will have additional stakeholders with no representation at the upper levels, such as interest-specific citizens’ groups or third parties involved in project execution. Nonetheless, almost every project has a core group of stakeholders with representation at higher levels. This provides project stability and alignment to program and higher levels, but could also create dramatic impacts generated by external factors, such as government or political direction changes.
1.4 Structure of the Government Extension
The Government Extension to the PMBOK® Guide Third Edition is organized into the following three sections:
1.4.1 Section I:—The Project Management Framework
Section 1, “The Project Management Framework,” provides a basic structure for understanding project management in the government sector.
Chapter 1, Introduction, defines key terms and provides an overview for the rest of the Government Extension.
Chapter 2, Project Life Cycle and Organization, describes the environment in which government projects operate. The project management team should understand this broader context. Managing the day-to-day activities of the project is necessary, but not sufficient, to ensure success.
1.4.2 Section II:—The Standard for Project Management of a Project
Section II, “The Standard for Project Management of a Project,” specifies all the project management processes that are used by the project team to manage a government project.
Chapter 3, Project Management Processes for a Project, describes the five required Project Management Process Groups for any project and their constituent project management processes. This chapter describes the multidimensional nature of project management.
1.4.3 Section III:—The Project Management Knowledge Areas
Section III, “The Project Management Knowledge Areas,” organizes the forty-four project management processes from Chapter 3’s Project Management Process Groups into nine Knowledge Areas. An introduction to Section III describes the legend for the process flow diagrams used in each Knowledge Area chapter, and also provides introductory material applicable to all nine Knowledge Areas.
Chapter 4, Project Integration Management, describes the processes and activities that integrate the various elements of project management that are identified, defined, combined, unified, and coordinated within the Project Management Process Groups. It consists of the Develop Project Charter, Develop Preliminary Project Scope Statement, Develop Project Management Plan, Direct and Manage Project Execution, Monitor and Control Project Work, Integrated Change Control, and Close Project project management processes.
Chapter 5, Project Scope Management, describes the processes involved in ascertaining that the project includes all the work required, and only the work required, to complete the project successfully. It consists of the Scope Planning, Scope Definition, Create Work Breakdown Structure (WBS), Scope Verification, and Scope Control project management processes.
Chapter 6, Project Time Management, describes the processes concerning the timely completion of the project. It consists of the Activity Definition, Activity Sequencing, Activity Resource Estimating, Activity Duration Estimating, Schedule Development, and Schedule Control project management processes.
Chapter 7, Project Cost Management, describes the processes involved in planning, estimating, budgeting, and controlling costs so that the project is completed within the approved budget. It consists of the Cost Estimating, Cost Budgeting, and Cost Control project management processes.
Chapter 8, Project Quality Management, describes the processes involved in assuring that the project will satisfy the objectives for which it was undertaken. It consists of the Quality Planning, Perform Quality Assurance, and Perform Quality Control project management processes.
Chapter 9, Project Human Resource Management, describes the processes that organize and manage the project team. It consists of the Human Resource Planning, Acquire Project Team, Develop Project Team, and Manage Project Team project management processes.
Chapter 10, Project Communications Management, describes the processes concerning the timely and appropriate generation, collection, dissemination, storage, and ultimate disposition of project information. It consists of the Communications Planning, Information Distribution, Performance Reporting, and Manage Stakeholders project management processes.
Chapter 11, Project Risk Management, describes the processes concerned with conducting risk management on a project. It consists of the Risk Management Planning, Risk Identification, Qualitative Risk Analysis, Quantitative Risk Analysis, Risk Response Planning, and Risk Monitoring and Control project management processes.
Chapter 12, Project Procurement Management, describes the processes that purchase or acquire products, services or results, as well as contract management processes. It consists of the Plan Purchases and Acquisitions, Plan Contracting, Request Seller Responses, Select Sellers, Contract Administration, and Contract Closure project management processes.
1.5 Areas of Expertise
See Section 1.5 of the PMBOK® Guide—Third Edition.
1.5.1 Project Management Body of Knowledge
See Section 1.5.1 of the PMBOK® Guide—Third Edition.
1.5.2 Application Area Knowledge, Standards, and Regulations
See Section 1.5.2 of the PMBOK® Guide—Third Edition.
1.5.3 Understanding the Project Environment
See Section 1.5.3 of the PMBOK® Guide—Third Edition.
1.5.4 General Management Knowledge and Skills
See Section 1.5.4 of the PMBOK® Guide—Third Edition.
1.5.5 Interpersonal Skills
See Section 1.5.5 of the PMBOK® Guide—Third Edition.
1.6 Project Management Context
See Section 1.6 of the PMBOK® Guide—Third Edition.
1.6.1 Programs and Program Management
See Section 1.6.1 of the PMBOK® Guide—Third Edition, with an understanding that programs are generally more common in government than in the private sector. In government programs, there is often far more emphasis on the ongoing operations described in the PMBOK® Guide—Third Edition definition and, in some cases, some government bodies classify ongoing operations themselves as a program. Further, some governments also treat programs like portfolios of projects. Unlike commercial programs, government programs are used to set social goals, provide social services, and set priorities through public discourse (meetings and voting) and accountability (audits, hearings, legal actions, and the press).
Government bodies, especially larger governments, generally appropriate funds to programs rather than to individual projects. On regional or national levels, the legislative body sets program goals and priorities but can not review the details of every project. For example, such bodies may appropriate funds for a program of school improvements, with rules for how the funds are to be divided among individual projects. The government body has the authority to fund and then later redirect (reprogram) program funding to other purposes, provided there is a majority in agreement to do so.
On the other hand, in smaller governments, the legislative body may appropriate funds for individual projects and/or programs. A local body may, for instance, appropriate funds for an individual project involving a new classroom at a local school or a program for school improvements. The use of public funding, public accountability and setting of social goals that are measured in social good rather than return on investment make government programs unique.
1.6.2 Portfolios and Portfolio Management
See Section 1.6.2 of the PMBOK® Guide—Third Edition, with an understanding that portfolios of projects are very common in smaller government bodies where each project can be approved, funded, and monitored individually. Managing and monitoring them as portfolios allows the budgetary authority to have an overall view of the entire budget execution, and redistribute funds as needed to achieve maximum benefits for their constituents.
1.6.3 Subprojects
See Section 1.6.3 of the PMBOK® Guide—Third Edition.
1.6.4 Project Management Office
See Section 1.6.4 of the PMBOK® Guide—Third Edition.
1.7 Explanation of Government Extension Processes: Inputs, Tools & Techniques, and Outputs
This document follows closely the structure and organization of the PMBOK® Guide—Third Edition. This enables easier cross-referencing between equivalent sections of this extension and the PMBOK® Guide.
The PMBOK® Guide—Third Edition describes the inputs, tools and techniques, and outputs of each project management process. For each process, it includes a table that lists three types of elements. This document includes similar tables. In each table, the elements have the following format: