Activity duration, estimating, 68–69
Actual cost (AC), 97
American Physical Plant Association, 69
Analogous estimating method, 83
Baseline consolidated project plan, 89–90
Bottom-up estimating method, 84
Budget, 86–88
controlling, 97
Budget at completion (BAC), 97
Change control
establishing, 61–62
template, 62
Close project
deliverables, transitioning, 106
lessons learned, capturing and sharing, 106–107
post-project activities, completing, 107
Communication
appropriate, using, 102–106
managing, 101–106
needs, understanding, 102
Contingency reserve, 85
Core team members, 9
Cost(s)
contingencies and uncertainty, 85
estimation methods, 83–84
life cycle, 82
and sustainability, 82
types of, 82–83
Cost performance index (CPI), 98, 99
Critical path, identification of, 72–73
Decomposition, 54
Deliverables, transitioning, 106
Direct costs, 82–83
Direct supervisor of project manager, responsibilities of, 11
Earned value analysis (EVA), 95, 97–100, 117
Estimate at completion (EAC), 98, 99
Estimate to complete (ETC), 98, 99
Face-to-face conversations, 102
Fixed costs, 83
Gantt chart, 73–75, 77, 86, 103, 104, 115
A Guide to the Project Management Body of Knowledge (PMBOK Guide®), 23
Indirect costs, 83
Integrated plan, 89
International Facility Manager’s Association, 69
Key roles, in project management, 8–11
Kickoff project, 89
Known knowns, 58–59
Lessons learned, capturing and sharing, 106–107
Life cycle costs, 82
Management reserve, 85
Parametric estimating method, 83–84
Planned value (PV), 97
Portfolio management, 17–20
Post-project activities, completing, 107
Prioritizing projects, 20, 121
Progress reports, 103–105, 117
Project change
controlling, 100–101
Project charter, 21–32
components of, 22–23
construction of, 23–30
draft charter, approving, 30
example of, 27–30
milestone schedule with acceptance criteria template, 25
reasons for using, 21–22
Project, definition of, 1
roles and responsibilities template, 11, 110
Project management
definition of, 1–2
key roles in, 8–11
Project Management Institute Code of Ethics & Professional Conduct, 11, 82
Project Management Office (PMO), 20–21, 32
Project manager (PM)
responsibilities of, 11
Project performance
changes, controlling, 100–101
communications, managing, 101–106
directing, 94
monitoring and controlling, 94–95
quality assurance, 95
quality control, 95–96
risks, monitoring and controlling, 96
schedule and budget, controlling, 97
Project schedule(ing), 65–80
activity duration, estimating, 68–69
controlling, 97
developing, 69–73
critical path, identification of, 72–73
second pass (backward), 70–72
on Gantt chart, showing, 73–75
limitations of, 65
resource overloads, identifying, 77–78
using software, 78–79
work activities, defining, 66
work activities, sequencing, 66–68
workers, assigning, 75–76
Project success, 3–4
template, 109
Project team, 35–40
attitude and skill development stages, 38
development of, 38
leading, 39–40
location of, 36–37
misunderstandings, 36
resource sharing, 36
team members, evaluation of, 36
team members needs and secure commitment, identifying, 37–38
Proposing projects, 18–19
Quality assurance, 95
Quality control, 95–96
Requirements
collection of, 49–52
Resource availability matrix, 118, 119–120
Resource overloads, identifying, 77–78
Resource sharing, 36
matrix, 123
Risk
assessment, 60
categories of, 58–59
management, 58–60
monitoring and controlling, 96
response plan, 61
Schedule performance index (SPI), 98, 99
Schedule variance (SV), 97, 99
Scope, 52–54
constraints and assumptions of, 53–54
definition of, 52
and project life cycle, 53
Second pass (backward), 70–72
Selecting projects, 20
Silos, 44
Software, project scheduling using, 78–79
Sponsor, responsibilities of, 11
Stakeholders
building relationships with, 42–43
communication with, 43–46, 113
identification of, 40
prioritizing, 40–41
Stand-up meetings, 102
Subject matter experts (SMEs), 9, 37
Sustainability, costs and, 82
Team members
evaluation of, 36
needs and secure commitment, identifying, 37–38
To-complete performance index (TCPI), 98, 100
Total cost spreadsheet, 116
Value engineering, 85
Variable costs, 83
Work activities
defining, 66
duration of, estimating, 68–69
sequencing, 66–68
Work breakdown structure (WBS), 65, 84
creation of, 54–57
free form format, 56
indented outline format of, 55
org chart format, 56
participation, ensuring, 57–58
Workers, assigning, 75–76