184 ◾ PfMP® Exam Practice Tests and Study Guide
71. d. Are recommended for consideration by the Portfolio Review Board
Portfolio reports are an output of the Manage Portfolio Value process.
In this situation, these cost savings and the actions recommended then
require consideration from governance.
Portfolio Management Standard, p. 104
Task 9 in the ECO in Performance
72. d. Goals
Organizations establish goals to move to their desired vision. Goals
have objectives that then are measured, and strategies are developed to
achieve goals.
Portfolio Management Standard, p. 7
Task 8 in the ECO in Strategic Alignment
73. a. Portfolio strategic plan
The purpose of the portfolio strategic plan in this situation is to provide
guidance as it describes the portfolio vision and objectives, benets, key
risks, assumptions, and constraints.
Portfolio Management Standard, p. 48
Task 1 in the ECO in Performance
74. c. Is used to authorize the portfolio
Governance decision reports are an example of portfolio reports, an
input to the Authorize Portfolio process. These reports authorize com-
ponents and provide detailed information on why the component
was selected.
Portfolio Management Standard, p. 79
Task 5 in the ECO in Governance
75. a. Visualize components
Bubble diagram graphs are an example of a graphical analytical method
used as a tool and technique in Optimize Portfolio. The bubbles repre-
sent components, both existing and proposed, according to predened
balancing criteria.
Milosevic, pp.74–75
Portfolio Management Standard, pp.75–76
Task 7 in the ECO in Performance