18.4.7. Systematic fault analysis using Zbus matrix

For large networks, this method is applicable. Consider the network shown in Figure 18.32. Assume a three-phase fault at bus k has occurred through fault impedance Zf.
image
Figure 18.32 Fault at bus k.
Prefault-bus voltages are obtained from load-flow solution and are a column vector.

Vbus(0)=V1(0)Vk(0)Vn(0)

image
Short circuit currents are larger than steady-state values and hence can be neglected. Represent the bus load by a constant impedance evaluated at the prefault bus voltage, that is,

ZiL=Vi(0)2SL2.

image
The change in network voltage caused by fault in impedance Zf, is equivalent to those caused by the added voltage Vk(0) with all other sources short circuited. The bus voltage changes caused by the fault in this circuit are represented by:

_Vbus(0)=_V1(0)_Vk(0)_Vn(0).

image
Using Thévenin’s theorem, bus voltages during the fault are obtained by superposition of the prefault bus voltages and changes in bus voltages are given by,

Vbus(F)=Vbus(0)+_Vbus

image
It is known that Ibus = YbusVbus.
Current entering every bus is zero except at the faulty bus. As the current leaves the faulty bus, it is taken as negative current entering bus k:

0Ik(F)0=Y11Y1kY1nYk1YkkYknYn1Yn1Ynn_V1_Vk_VnIbus(F)=YbusVbus.

image
Solving for ∆Vbus,

Vbus=ZbusIbus(F)therefore,Vbus(F)=Vbus(0)+ZbusIbus(F)forfaultinbusk,thebusvoltage,Vk(F)=Vk(0)ZkkIk(F)andfaultcurrentisIk(F)=Vk(0)Zkk+Zf.

image

18.5. Power flow study

The load flow analysis is required to be performed to decide upon addition/removal of a substation, distribution transformers, tap changers, reactive power controlling devices, etc. From the conservation of energy, real power supplied by the source is equal to the sum of real powers absorbed by the load and real losses in the system. Reactive power must also be balanced between the sum of leading and sum of lagging reactive power-producing elements. The total complex power delivered to the loads in parallel is the sum of the complex powers delivered to each,

0=PgenPloadsPlosses0=Qleading+QcapsQlaggingQind0=SgenSloadsSlosses.

image
Complex power injected into the ith bus is Si = Pi + jQi = ViIi* and i = 1, 2, …, n where, Vi is the voltage at the ith bus and Ii is the source current injected into the bus,
Hence Si=PijQi=Vi*Ii=Vi*k=1nYikVk.image
Therefore, Pi=realVi*k=1nYikVk.image

Qi=imVi*k=1nYikVk

image
In polar form Vi=ViejδiandYi=Yikejqikimage.

Pi=Vik=1nYikVkcosθikδi+δkQi=Vik=1nYikVksinθikδi+δk.

image
The P and Q equations are known as static load flow equations. To solve the static load flow equations, no explicit solutions are possible with the variables: Pi, Qi, |Vi|, δI, as it involves trigonometry and only iterative solutions.

18.5.1. Load flow equations and methods of solution

Load flow solution is a solution of the network under steady-state condition subject to certain inequality constraints, under which the system operates. These constraints can be in the form of load nodal voltages, reactive power generation of the generators, the tap settings of a tap changing under load transformer, etc. To solve the load flow equation, the buses are classified as in Table 18.1:

0=PgenPloadsPlosses

image

Table 18.1

Bus classification

Bus type Quantities specified To be obtained
Load bus P, Q |V|, δ
Generator bus or voltage controlled bus P, |V| Q, δ
Slack bus/swing or reference bus |V|, δ P, Q
But loss remains unknown until the load flow equation is solved. Hence, one of the generator buses is made to take up additional real and reactive power to supply transmission loss and is named as swing bus. It is known that Ibus = [Ybus]Vbus, where V and Y are obtained from the prefault-bus voltage and bus-admittance matrix, as discussed in the previous topics.
image
where image and Yip=Yipγipimage.
Complex power injected into the ith bus is,
image
The static load-flow equation can be rewritten as,

Realpart=Pi=Vip=1nVpYipcosδiγipδpImaginarypart=Qi=Vip=1nVpYipsinδiγipδp.

image

18.5.2. Solution of load flow equation

Xik=fi(X1k,X2k,Xi1k,Xik1,Xi+1k1,Xnk1)Xi=XikXik1Xik=Xik1+aXi.

image
Its advantages are,
1. Simplicity of the technique.
2. Small computer memory requirement.
3. Less computation time per iteration.
Its disadvantages are,
1. Slow rate of convergence, therefore large number of iterations.
2. Increase in number of iterations directly with increase in number of buses.
3. Effect on convergence due to choice of slack bus.
Hence, Gauss–Seidel (G–S) method is used only for systems having a small number of buses.

18.5.2.1. Using Gauss-Seidel (G-S) method when PV buses are absent

Out of n buses, 1 is the slack bus, so n – 1 PQ buses.

Ii=YiiVip=1nYipVpVi=1YiiIip=1nYipVp.

image
Similarly,

Si*=PijQi=Vi*IiIi=PijQiVi*Vi=1YiiPijQiVi*p=1nYipVpi=2,3,n,since1isaslackbus.

image
Solve for V2, V3, …, Vn,

Ki=PijQiYiiLip=YipYiii=2,3,np=1,2,npnVik+1=Ki(Vik)*p=1nLipVpk+1p=i+1nLipVpki=2,3,n.

image

Problem 18.13

The following is the system data for a load flow solutions. The line admittances are,
Bus code Admittance
1–2 2–j8.0
1–3 1–j4.0
2–3 0.666–j2.664
2–4 1–j4.0
3–4 2–j8.0
The schedule of active and reactive powers,
Bus code P Q V Remarks
1 1.06 Slack
2 0.5 0.2 1 + j0 PQ
3 0.4 0.3 1 + j0 PQ
4 0.3 0.1 1 + j0 PQ

Determine the voltages at the end of first iteration using G–S method. Take =1.6image,

Ybus=3j122+j81+j402+j83.666j4.6640.666+j2.6641+j41+j40.666+j2.6643.666j14.6642+j801+j42+j83j12.

image
Power for load buses is negative, generation buses is positive,

V21=1Y22PiJQiYiiY21V10Y23V30Y24V40=13.666j14.6640.5+j0.21j01.06(2+j8)1(0.666j2.664)1(1+j4)=1.01187j0.02888V'2acc=(1+j0)+1.6(1.01187j0.028881j0)V'3=1Y33P3JQ3V3*Y31V1Y32V'2Y34V40=13.666j14.6640.4+j0.31j0(1+j4)1.06(0.666+j2.664)(1.01899j0.046208)(2+j8)(1+j0)=0.994119j0.029248V'3acc=0.99059j0.0467968V'4=1Y44P4JQ4V4*Y41V1Y42V'2Y43V'3=0.9716032j0.064684V'4acc=0.954565j0.1034944

image

18.5.2.2. Modification of G–S method when PV buses are present

Now, i = 1 slack bus, i = 2, 3, …, m PV bus, and i = m + 1, …., n PQ bus.
Conditions to be met by PV buses are:
1. |Vi| = |Vi|specified for i = 2, 3,…, m
2. Qi,min < Qi < Qi,max for i = 2, 3,…, m.
The second requirement can be violated if the specified bus voltage |Vi|specified is either too high or too low. It is possible to control |Vi| only by controlling Qi. Hence, if Q constraint is violated, treat it as a PQ bus with Q equal to maximum or minimum values.
Steps:
1. Calculate Qi=Vip=1nVpYipsinδiγipδpimage
2. For every iteration |Vi| must be set equal to |Vi|specified.
3. Qik+1=Vispecifiedp=1i=1Vpk+1Yipsinδikγipδpk+1+Vispecifiedp=inVpkYipsinδikγipδpkimage.
4. Check for constraints, if violated, treat as PQ bus.

Problem 18.14

If in Problem 18.13, bus two is taken as a generator bus with |V2| = 1.04 and reactive power constraint is 0.1 ≤ Q2 ≤ 1.0, determine the voltages starting with a flat voltage profile and assuming the accelerating factor as 1.
Since bus two is a PV bus, Q is not specified. Hence, to find V2′, Q2 must be calculated, with
V2 = 1.04 and the phase angle of voltage = 0.

P2jQ2=V2*q=14Y2qVq=V2*[Y21V1+Y22V2+Y23V3+Y24V4]Q2=1.04[Y21V1sin(δ1γ21δ2)+Y22V2sin(δ2γ22δ2)+Y23V3sin(δ2γ23δ3)+Y24V4sin(δ2γ24δ4)]=0.1108.

image
Since Q2 lies within limits, V2 = V2specified:

V2=1Y220.5j0.11081.04j0Y22V1Y23V3Y24V4V2'=1.0472846+j0.0291476,δ=1.59°V2=1.04=1.0395985+j0.02891159V2acc'=negativeV3'=1Y33R3jQ3V3Y31V1Y32V2'Y34V4=0.9978866j0.015607057=0.998065j0.022336.

image

Problem 18.15

For the same problem, if the reactive power constraint on generator two is 0.2 ≤ Q2 ≤ 1, solve the problem for voltages at the end of the first iteration.
Q2 = 0.1108. Hence, violated. So assume as PQ bus with P2 = 0.5, Q2 = Q2min = 0.2, and V2°image = 1 + j0 and as usual procedure, but P2 + jQ2 is positive, though it is assumed to be a PQ bus.

V2'=1Y220.5j0.21j0Y22V1Y23V3°Y24V4°=1.098221+j0.030105.

image
Similarly V3'image and V4'image are calculated.

18.5.2.3. Newton–Raphson method

It is suitable for large systems.
Its advantages are:
1. Increased accuracy and surety of convergence.
2. Only about three iterations are required compared to more than 25 or so required by the G–S method.
3. Number of iterations is independent of system size.
4. This method is insensitive to factors like slack bus selection, regulating transformers, etc.
Its disadvantages are:
1. Solution technique is difficult.
2. More calculations are involved, hence more computation time/iteration.
3. Memory requirement is large.
This method can be used with both rectangular and polar coordinates. But the rectangular coordinate requires more number of equations as compared to the polar form. Hence, the polar form is preferred.
N–R method using rectangular coordinates is,
image
Changes in active and reactive power with bus as slack,

Pi=p=2npilplp+p=2npilpfpQi=p=2nQilplp+p=2nQifpfp.

image
PQ=j1j2j3j4efimage for PV bus |Vi|2 = ei2 + fi2.
Vi2=|Vi|2ρiρi+|Vi|2fifiimage with PV bus (instead of Qi and Vi).
Total number of equations = (n – 1)2.
N–R method using polar coordinates is,

Pi=f1(δ,|V|),Qi=f2(δ,|V|).

image

Pi=p=2npiδp·δp+p=2npi|Vp|·|Vp|.

image(18.1)

Qi=p=2nQiδp·δp+p=2nQi|Vp|·|Vp|.

image(18.2)
but for PV bus (18.2) does not exist.
The n bus system has 1 slack bus and g PV buses.
Total number of equations = (2n – 2 – g).
Therefore,

PiδpQiδp=j(eijfi)(Gip+jBip)(ep+jfp)

image
Replace ∆Vp by, VpVpimage

Pi=p=2npiδpδp+p=2npi|Vp||Vp|VpVpQi=p=2nQiδpδp+p=2nQi|Vp||Vp|VpVpPQ=HNJLδVVHip=piδpNip=pi|Vp||Vp|Jip=QiδpLip=Qi|Vp||Vp|PijQi=Vi*p=1nYipVp...(*).

image
Hence, a Jacobian matrix can be formed from Ybus:

Y=G+JBVi=ei+jfiapjbp=(Gip+jBip)(ep+jfp)piδp=Hip=apfibpeiJip=(apei+bpfi)Hii=QiVi2BiiJii=PiVi2GiiNip=JipandLip=HipNii=Pi+Vi2GiiandLii=QiVi2BiiPijQi=Viejδ1p=1nYipejγLpVpejδppiδpjQiδp=j(Viejδ1)(YipejγLp)(Vpejδp)Viejδ1=eijfiYipejγLp=Gip+jBipVpejδp=ep+jfp.

image

Problem 18.16

Figure 18.33 shows a six-bus system. Assuming bus one is a slack bus, formulate the Jacobian matrix for this system.
image
Figure 18.33 Six-bus system for Problem 18.16.
Using the following conventions, the Jacobian matrix is formulated.
If bus i and bus m are both PQ buses, then all the Jacobian components are present.
If bus i is a PQ bus and bus m is a PV bus, then the Jacobian components present are Him and Jim.
If bus i is a PV bus and bus m is a PQ bus, then the Jacobian components present are Him and Nim.
If bus i and bus m are both PV buses, then the Jacobian component present is only Him as ∆|Vm| = 0.

P2Q2P3P4Q4P5P6Q6=H22N22H23H24H24J22L22J23J24L24H23N23H33H35H36N36H42N42H44N44N45J42L42J44L44J45H53H54N54H55H56H56H63H65H66N66J63J65J66L66

image

Problem 18.17

Figure 18.34 shows a five-bus system. Assuming bus one is a slack bus, formulate the Jacobian matrix for this system:

H22N22H23H24H240J22L22J23J24L240H32N32H3300H35H42N420H44N44H45J42L420J44L44J4500H53H54N54H55

image
image
Figure 18.34 Five-bus system for Problem 18.17.

Problem 18.18

Determine the set of load flow equations at the end of first iteration using NR method. The load flow data for the given power system are given next. The voltage magnitude of bus 2 is to be maintained at 1.04 pu. The maximum and minimum reactive power limits of the generator at bus 2 are 0.35 and 0 pu, respectively.
Bus code Assumed voltages Generation Load
MW MVAR MW MVAR
1 1.06 + j0 0 0 0 0
2 1 + j0 0.2 0 0 0
3 1 + j0 0 0 0.6 0.25

The admittance matrix is given as:

Ybus=6.25j18.751.25+j3.755+j151.25+j3.752.916j8.751.666+j55+j151.666+j56.666j20

image

Solution

From the admittance matrix, it is observed that:
G11 = 6.25 G12 = −1.25 G13 = −5 G22 = 2.916 G23 = −1.666 G33 = 6.666
B11 = 18.75 B12 = −15 B13 = −15 B22 = 8.75 B23 = −5 B33 = 20

The voltage amplitude and phase angle of the bus are specified as:
e1 = 1.06 e2 = 1 e3 = 1 f1 = 0 f2 = 0 f 3 = 0

From the static load flow equations, active power in bus 2 can be calculated as follows. θ values are taken from the admittance matrix written in polar coordinates form.

P2=V2V1Y21cos(θ21+δ1δ2)+V22Y22cos(θ22)+V2V3Y23cos(θ23+δ3δ2)=0.075

image
Alternately, the active and reactive power can also be calculated as follows.

PijQi=(ei+jfi)*p=1n(GipjBip)(ep+jfp)=(eijfi)*p=1n(GipjBip)(ep+jfp)

image

Pi=p=1nei(epGip+fpBip)+fi(fpGipepBip)

image

Qi=p=1nfi(epGip+fpBip)ei(fpGipepBip)

image

P2=e2(e1G21+f1B21)+f2(f1G21e1B21)+e2(e2G22+f2B22)+f2(f2G22e2B22)+e2(e3G23+f3B23)+f2(f3G23e3B23)=0.075

image
Similarly the active and reactive powers of bus 2 and 3 are calculated.
P3 = −0.3 Q2 = −0.225 Q3 = −0.9
The ∆ values are the difference between specified values and the calculated values. Hence,
P2 = 0.275 P3 = −0.3 Q2 = 0.225 Q3 = 0.65

Q2 violates the limits specified, therefore bus 2 is treated as load bus with Q2spec = 0.

Ppep=2epGpp+q=1qpnepGpq+fqBpq

image

P2e2=2e2G22+q=1q23e2G2q+fqB2q

image

P2e2=2e2G22+[e2G21+f2B21+e2G23+f3B23  =2x1x2.916+1.06(1.25)+0(3.75)+1(1.66)+0(5)=2.848

image
Similarly, P3e3=6.367image

Ppfp=2fpGpp+q=1qpnfqGpq+eqBpq

image

P2f2=2f2G22+[f1G21e1B21+f3G23e3B23]=8.975

image
Similarly, P3f3=20.9image

Ppeq=epGpqfpBpq

image

P2e3=1.666

image

P3e2=1.666

image

Ppfq=epBpq+fpGpq

image

P2f3=5.0

image

P3f2=5.0

image

Qpep=2epBpp+q=1qpnfqGpqeqBpq

image

Q2e2=8.525

image

Q3e3=19.1

image

Qpfp=2fpBpp+q=1qpneqGpq+fqBpq

image

Q2f2=2.991

image

Q3f3=6.966

image
At the end of first iteration, the load flow equations are:

0.2750.30.2250.65=2.8461.6668.9755.01.6666.3665.020.908.5255.02.9911.6665.019.11.6666.966e2e3f2f3

image

Problem 18.19

Consider the three-bus system. Each of the three lines has a series impedance of 0.02 + j0.08 pu and a total shunt admittance of j0.02 pu. The specified quantities at the buses are tabulated below.
Bus Real load demand (PD) Reactive load demand (QD) Real power generation (PG) Reactive power generation Voltage specified
1 2 1 1.04 + j0
2 0 0 0.5 1 (PQ)
3 1.5 0.6 0 ? V3 = 1.04 (PV)

A controllable reactive power source is available at bus three with the constraint 0 ≤ QG3 ≤ 1.5 pu. Find the load flow solution using the N–R method; use a tolerance of 0.01 for power mismatch.
1.

Ybus=24.2375.9512.13104.0412.13104.0412.13104.0424.1375.9512.13104.0412.13104.0412.13104.0424.2375.95P2=V2V1Y12cos(θ21+δ21δ2)+V22Y22cos(θ22)+V2V3Y23cos(θ23+δ3δ2)P2=0.063pu,P3=0.122puQ2=0.224pu,Q3=0.557puJ=H22H23N23H32H33N33J32J33L33H22=Q2V22B22=0.2241.032(17.18)=18.002a3+jb3=(G23+jB23)(a3+jb3)=2.035+j8.61H23=a3f2b3e2=8.868J=18.0028.8682.0358.86817.7363.9482.0964.19216.623

image
2.P2 = P2specP2calc = 1.5 – 0.063 = 1.437 pu
P3 = –1.2 – (–0.122) = –1.078 pu
Q3 = –0.5 – (–0.557) = 0.057 pu

1.4371.0780.057=18.0028.8682.0358.86817.7363.9482.0964.19216.623δ2δ2V3V3

image

18.5.2.4. Fast decoupled load flow method

Sparsity of YBus and loose physical interactions between MW and MVAR flows are taken to make load-flow studies faster and more efficient. Pδ and QV are strong whereas PV and Qδ are weak. Therefore, MW–δ MVAR–V calculations are decoupled and hence N and J are neglected in the Jacobian matrix:

[P]=[H][δ][Q]=[L]VV.

image
Voltage angle corrected using P
Voltage magnitude corrected using Q

yipejyLp=Gip+jBippiδpjQiδp=jViVpej(δpδi)(Gip+jBip)

image
But δpδi is very small. Hence, ej(δpδi) ≈ 1.
1. cos(δpδi) ≈ 1 and sin(δpδi) = (δpδi).
Therefore,

piδpjQiδp=jViVp(Gip+jBip)

image
Separating real and imaginary terms where Ip:
2. Hip=piδp=ViVpBipbutL=HLip=Hip=ViVpBipimage.
In the expressions for Lii and Hii, Qi is generally very small compared to |Vi|2 Bii:

QiVi2BiiHii=Lii=Vi2Bii[P]=[VB'V][δ][Q]=[VBV]VV

image
B′ and B99 elements [–Bip].
In the PV bus, Q is not specified and ∆|V| = 0.
Therefore such rows can be simply neglected.
The final algorithm is obtained by making the following approximations.
1. Omit from [B′] the representation of those network elements, which predominantly affect MVAR flow only and do not affect MW flow significantly, that is, shunt reactance, off nominal Xr.
2. Omit from [B99] the angle shifting effects of phase shifters.
3. Neglect the series resistance is calculating the elements of [B]. With these modifications:

PV=B'[δ]QV=B[V].

image
B′ and B99 are real and sparse.

18.5.2.5. Fixed slope decoupled Newton–Raphson

Load flow computations in a large system are,
1. sparsity: 97% sparse,
2. slope only diagonal and off diagonal + row, column matrix,
3. Gauss elimination, triangular factorization,
4. optimal ordering – least zero, most nonzero number, hence row to be eliminated is with least zero elements.

18.5.2.6. Load flow solution for microgrids

Load flow is the procedure used for obtaining the steady-state voltages of electric power systems at fundamental frequency. An efficient power flow solution looks for fast convergence, minimum usage of memory (computationally efficient), and a numerically robust solution for all the scenarios. Load flow studies on transmission networks are well developed using G–S and N–R methods and their decoupled versions. Because of the some of the following special features the distribution networks fall in the category of ill-conditioned power systems for these conventional load flow methods.
Radial or weakly meshed networks.
High R/X ratios.
Multiphase, unbalanced operation.
Unbalanced distributed load.
Distributed generation.
A single-phase representation of three-phase system is used for power flow studies on a transmission system that is assumed as a balanced network in most cases. But the unbalanced loads, radial structure of the network, and untransposed conductors make the distribution system as an unbalanced system. Hence, three-phase power flow analysis needs to be used for distribution systems. The three-phase power flow analysis can be carried out in two different reference frames, namely, phase frame and sequence frame. Phase frame deals directly with unbalanced quantities and sequence frame deals with three separate positive, negative, and zero sequence systems to solve the unbalanced load flow conditions in the circuit. Load flow analysis in distributed generation is carried out using the forward and backward sweep method, compensation methods, implicit Z bus method, direct method (bus injection to branch current and branch current to bus voltage matrices method), or modified Newton methods.

18.6. Power system stability

The dynamics of power systems with the continuous load variations and varying power generation capacity impacts on the stability of the system. Power system stability is the ability of the system to bring back its operation to a steady-state condition within the minimum possible time if undergoing a transient or other disturbance in the system. In power plants, synchronous generators with different voltage ratings are connected to the bus terminals having the same frequency and phase sequence. For example, consider the case defined in the Problem 18.19. After careful analysis, it is found that synchronization depends upon load sharing based on the droop characteristics of the generator. The same is also true for microgrids.

Problem 18.20

Two generators rated 200 and 400 MW are operating in parallel. The droop characteristics shown in Figure 18.35, of their governors are 4 and 5%, respectively, from no load to full load. Assuming that the generators are operating at 50 Hz at no load, how would a load of 600 MW be shared between them? What will be the system frequency at this load?
image
Figure 18.35 Droop characteristics.
As the generators run in parallel, they operate at the same frequency.
Let load on G1 (200 MW) = x MW and load on G2 (400 MW) = (600 – x) MW.
Reduction in frequency = ∆f,

fx=0.04×50200f600x=0.05×50400.

image
Equating the ∆f and solving, x = 231 MW. Therefore the load on G1 is 231 MW (overloaded) and that of generator two is 369 MW (underloaded). The system frequency will be,

Systemfrequency=500.04×50200×231=47.69Hz.

image
As the droop characteristics are different, G1 is overloaded and G2 is underloaded. If both the governors are 4% droop then they will share the load as 200 and 600 MW, respectively.
Apart from this, stable and quality power is required for ICT applications and therefore stability analysis is important. The steady-state power limit defines the maximum power permissible to flow through a part of the system when subjected to a fault or disturbances. Stability analysis is done under various types of disturbances,
1. Steady-state stability – ability of a system to maintain its stability following a small disturbance like normal load fluctuations, action of automatic voltage regulator, etc., where the variations are gradual and infinitely small power change.
2. Transient state stability – ability of the system to maintain its synchronism following a large disturbance like sudden addition or removal of a large load, switching operations, faults, or loss of excitation, which exists for a reasonably longer period of time.
Power system stability studies as shown in Figure 18.36 are classified based on the duration, such as, short-term or long-term disturbance, and the factors, such as, voltage, frequency, and rotor angle disturbing the stability of the power system.
image
Figure 18.36 Classification of power system stability.
Basic phenomena associated with rotor angle stability are,
1. imbalance between accelerating and decelerating generator torque,
2. temporary surplus energy stored in the rotating masses,
3. synchronizing torque limited by pullout torque,
4. loss of the synchronization.
Basic phenomena associated with voltage stability are,
1. increased reactive load reducing the voltage magnitude,
2. temporary load reduction,
3. reduction in transfer capability between areas,
4. if there is no solution to load flow, the voltage collapses.
Basic phenomena associated with frequency stability are,
1. connected load,
2. speed of the generators,
3. prime mover.

18.6.1. Power angle curve and the swing equation [6]

The steady-state power limit is defined by the equation,

P=EVX

image
where E is the generated voltage, V is the terminal voltage, and X is the transfer reactance.
The power P = Pm sin δ and the power angle curve are drawn as shown in Figure 18.37.
The dynamics of a generator depend on the inertia constant designated by the manufacturer and the kinetic energy developed while running.

Kineticenergy=12Mωs

image
where M is the moment of inertia in MJs/rad and ωs is the rotor speed in rad/s.
image
Figure 18.37 Power angle curve.
The kinetic energy is also defined as:

GH=Kineticenergy=12Mωs

image
where G is the machine rating in MVAbase and H is the inertia constant in MJ/MVA.
Considering the rotor angle (δ) torque, speed, flow of mechanical (Pm) and electrical (Pe) powers in a synchronous machine, the rotor dynamics are defined by the swing equation:

Md2δdt2=PmPe

image

18.6.2. Solutions of swing equation [7]

For steady-state and transient stability analysis, swing equations can be solved using,
1. Equal area criterion method: in a power angle curve, the accelerating area should be equal to the decelerating area for synchronism to be achieved and stability to be regained following the disturbance.
2. Numerical solution of swing equation: modified Euler’s method.

18.6.3. Stability analysis in microgrids [2]

Apart from active and reactive power control using FACTS controllers, a microgrid’s overall stability depends on voltage control. With a large number of microsources connected, microgrids suffer from reactive power oscillations without proper voltage control resulting in circulating currents. This circulating control is controlled by using voltage-reactive power (VQ) droop controllers. VQ droop controllers will increase the voltage set point if the microsource reactive current becomes predominantly inductive and decreases the set point if the reactive currents are predominantly capacitive. The reactive power limits are set by the apparent power rating of an inverter and active power output of the microsource.

18.7. Summary

This chapter introduced basic methods and algorithms to study the performance of power systems. Based on the results, solutions may be provided to improve the reliability and security of a power-system network.

Problems

1. A 300 MVA, 20 kV, 3φ generator has a subtransient reactance of 20%. The generator supplies a number of motors over a 64-km transmission line having transformers at both ends. The motors are all rated at 13.2 kV and are represented by two equivalent motors. The rated inputs to the motors are 200 MVA and 100 MVA, respectively. Both have a reactance of 20%. The 3φ transformer T1 is rated 350 MVA, 230/20 kV with a leakage reactance of 10%. T2 is composed of three numbers of 1φ transformers each rated 127/13.2 kV, 100 MVA with a leakage reactance of 10.1. Reactance of the transmission line is 0.5 Ω/km. Draw the one-line diagram, impedance diagram, and reactance diagram.

References

[1] Kothari DP, Nagrath IJ. Modern power system analysis. 4th ed New Delhi: Tata McGraw Hill Education Private Limited; 2011.

[2] Chowdhury S, Chowdhury SP, Crossley P. Microgrids and active distribution networks. London, UK: The Institution of Engineering and Technology; 2009.

[3] Wadhwa CL. Electrical power systems. New Delhi, India: New Age International (P) Ltd; 2007.

[4] Grainger JJ, Stevenson WD. Elements of power system analysis. Noida, India: Tata McGraw Hill; 2007.

[5] Gupta BR. Power system analysis and design. 3rd ed. Waterville, ME: Wheeler Publishers; 2003.

[6] Saadat H. Power system analysis. 3rd ed. Noida, India: Tata McGraw Hill; 2004: reprint.

[7] Weedy BM. Electric power systems. New York: John Wiley; 1987.

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset