20
CAPITAL INVESTMENT DECISIONS
Introduction and Key Concepts

CHAPTER INTRODUCTION

Capital investment decisions (CIDs) are some of the most important business decisions that managers make. Capital decisions are generally defined as relatively large investments that will have an economic life of several years. We will define capital investments broadly, including purchases of equipment, new product development projects, acquiring a product line or a company, and many others. The capital investment decision is a determination of whether the project is likely to create value for shareholders. In this chapter, we will introduce capital investments, evaluation, and key decision criteria, and outline the steps required to evaluate CIDs. In Chapter 21, we will cover advanced topics of CIDs, including dealing with risk and uncertainty, monitoring projects, and presenting capital investment decisions.

THE CAPITAL INVESTMENT PROCESS

A strong capital investment process is critical to ensure a thorough evaluation and decision. Figure 20.1 outlines key steps in an effective capital investment process.

Flow chart with boxes connected by arrows from idea generated to capital budget and to operating plan and from idea generated to cross functional team, to review, to implementation, and to post implementation review.

FIGURE 20.1 Capital Investment Process Overview

Companies should identify potential capital projects as part of their strategic and annual operating planning activities. The capital budget should be an important element of each plan. For strategic plans, the managers should look out three to five years and anticipate significant capital expenditures to support growth, strategic initiatives, and other requirements. Integrating the capital plan into the financial projections will afford the opportunity to review cash flow projections and determine the adequacy of returns over the strategic planning horizon.

For significant expenditures, a capital investment proposal (CIP) should be prepared to document key aspects of the project, including business justification, economic case, alternatives, and implementation plan. The scope of the CIP and the management approval level should scale with the size and importance of the project.

Business Case. The business case should define the strategic and business objectives that will be achieved or supported with this use of capital. In addition to passing certain economic tests, the project must be clearly linked to a strategic or operational objective. Some projects may make economic sense but be outside or even inconsistent with the strategic direction of the company.

Economic Case. All capital investment projects should be supported by financial projections and an economic evaluation. The financial projections should be based on the business case and implementation plan and include the following:

  • Estimated costs to purchase and start up the project.
  • Incremental revenues, costs, and capital requirements that result from undertaking the project.
  • Estimated salvage or terminal value at the end of the project life.

Alternatives. Most projects have several alternative courses of action. These should be explored as part of the capital investment decision and documented in the capital investment proposal. Reviewers should test the basis of selecting the recommended plan to ensure that this alternative provides the best balance of technical, business, and economic performance.

Implementation Plan. Execution and implementation are always critical success factors for any project. Capital projects should be supported with a detailed implementation plan. This plan will provide a road map to achieve the objectives of the capital investment. A good implementation plan is a strong indication that the project is well planned, including identification of resource requirements, risks, and alternatives. The implementation plan also provides a basis for monitoring and reviewing progress of the project. Identifying key assumptions, checkpoints, and go/no‐go decision points will also allow managers to consider redirecting or terminating projects that may be at risk. The characteristics of a good implementation plan are detailed in the sidebar.

Executive Review of Capital Investment Projects

Most companies require management approval for investments over a certain limit. Approval requirements typically escalate to higher levels of management, the board of directors, or even shareholders based on the nature and size of the investment and source of financing. The sidebar (“Executive Review of Capital Projects”) highlights key points that executives should consider in their evaluation of significant investments.

EVALUATING THE ECONOMIC MERITS OF CAPITAL INVESTMENTS

No matter how simple or complex the project, the same basic three steps should be employed to evaluate and select appropriate capital investments. The three steps are:

  1. Estimate relevant cash flows associated with the project.
  2. Measure the project's expected performance against investment decision rules.
  3. Accept or reject based on decision rules.

These three steps focus on the financial or economic part of the evaluation. Of course, there also needs to be a review of other business issues and to ensure the project is consistent with the firm's strategic direction, as described earlier.

Step 1: Estimate Relevant Cash Flows Associated with the Project

Economic evaluations should be based on projected cash flows. The first step will be to estimate the incremental investments and profit and loss (P&L) on the project, and then to estimate cash flows, reflecting the capital investment, depreciation, and working capital requirements.

Estimating both the acquisition or development cost and future cash flows of a project are by far the most important and most difficult part of CIDs. There are three categories of cash flow to consider for most projects: the initial cash outflow or investment, the stream of annual cash flows over the project's expected life, and a residual or terminal value at the end of the project (or projected cash flow).

The definition and application of incremental cash flows is a source of confusion in estimating relevant cash flows. Incremental revenues, investments, costs, and expenses should be limited to those that directly result from undertaking the project. The test is to identify those expenses and revenues that are not incurred if the project is not undertaken.

For significant and complex projects, we should utilize the techniques covered in developing long‐term projections of future business in Chapter 14.

Initial Investment

We need to estimate the total investment or cash outflows associated with the project. This can be as simple as the purchase cost of a new piece of equipment. However, if the machinery is shipped to us and includes freight, installation, setup, and training, then these costs also must be reflected as the total cost of acquiring the asset.

The project investment can become very complex and extend over several years. For example, the total design, approval, and construction of a new refinery or nuclear plant can extend for a decade or longer. Similarly, the development of a new product such as a prescription pharmaceutical can extend over many phases with a high degree of uncertainty of effectivity and approval by regulatory agencies. The investment in these cases may be very difficult to estimate.

All cash outflows must be considered, regardless of the accounting treatment. These include operating expenses (after tax), purchases of property and equipment, development of facilities, and working capital required to support the project.

Cash Flows over Project Life

The second set of cash flows to consider are the estimated annual cash flows over the project's life. For simple projects, such as purchasing a more efficient piece of manufacturing equipment, the savings may be as simple to define as reduced labor or scrap costs. At the other end of the spectrum are complex projects such as new products or the acquisition of a company. In both these cases, a complete set of financial projections would be required, including a complete P&L, balance sheet, cash flow statement, and supporting schedules (see Chapter 14, Long‐Term Projections).

Residual or Terminal Value

We need to estimate what, if any, value may exist at the end of the project's expected (or projected) useful life. For projects involving manufacturing or transportation equipment, the value at the end of life may be trade‐in, salvage, or resale value. For more complex and longer‐term programs such as the acquisition of a business or development of a product line, we must estimate the value of the business at the end of its useful life (or forecast horizon). This value may be a liquidation value if the business would be shut down and the remaining assets sold at liquidation value. If the business could be sold or continue to operate beyond the projected life or forecast horizon, then we need to estimate the terminal or post‐horizon value.

Capital Investment Examples

Case Study 1: Automate Manufacturing Process

Vance Pharmaceutical is considering automating a key part of its manufacturing process. The equipment will cost $100,000 and is expected to reduce manufacturing cycle time, improve yield, and decrease test costs.

What incremental cash flows are likely to result from undertaking this project? This project will probably involve the following incremental cash flow items, among others:

  • Cost of equipment
  • Installation cost
  • Reduced labor and test costs
  • Reduced material costs due to yield improvement
  • Increased depreciation expense
  • Increased taxes on profit improvement

Case Study 2: Develop and Introduce New Treatment

Vance Pharmaceutical is considering the development of a breakthrough treatment for procrastination. The project will require several years of development and will result in a significant increase in sales. The treatment can be produced in the company's existing facilities.

What incremental cash flows are likely to result from undertaking this project? This project will probably involve the following incremental cash flow items, among others:

  • R&D investment
  • Cost of FDA approval
  • Investment in manufacturing process
  • Distribution channel and training
  • Marketing and promotion
  • Revenue and profits
  • Working capital required to support program
  • Increased depreciation expense
  • Increased taxes on profit improvement

Step 2: Measure the Project's Expected Performance against Investment Decision Rules

A variety of measures or decision criteria are used to evaluate the economic characteristics of the investment. In addition to satisfying these economic tests, the project must also be justified on a business and strategic basis. The three most common measures are net present value (NPV), internal rate of return (IRR), and payback. In special situations, additional measures are utilized. Most of the decision rules are based on the economic principle of the time value of money (TVOM). Refer to Chapter 19 to review TVOM, discount rates (DRs), and cost of capital.

We illustrate the measurement criterion with the following simple example:

  • Project life: 5 years
  • Initial investment: $24,000
  • Projected after‐tax savings for 5 years: $8,000
  • Project terminates at end of year 5 with no residual value.
  • Discount rate: 10%

Net Present Value (NPV)

Net present value (NPV) utilizes the discounted cash flow methodology described in Chapter 19 to account for the time value of money and project risk. The cash flow for each year is discounted back to the equivalent value today (“year 1”) using a discount or hurdle appropriate for the risk level of the project. NPV is the sum of all discounted cash inflows and outflows. A positive NPV indicates that the project has a rate of return that exceeds the discount rate used, and therefore should be approved. A negative NPV indicates that the project has a return under the discount rate, and should not be undertaken.

TABLE 20.1 NPV Illustration image

Discount Rate (10%)
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6
Project Cash Flows:
Cash Inflows −24,000 8,000 8,000 8,000 8,000 8,000
Present Value Factor 0.91 0.83 0.75 0.68 0.62 0.56
Present Value −21,818 6,612 6,011 5,464 4,967 4,516
Net Present Value (Sum of PV) 5,751

In the example in Table 20.1, the NPV is +$5,751, indicating that the project has a return above the expected return (discount rate) and should be implemented. Note that we provided the present value factor (PVF) and present value (PV) for each annual cash flow. This provided insight into the TVOM and the dynamics of the project's NPV.

Internal Rate of Return (IRR)

The internal rate of return (IRR) of a project is the actual rate of return implied in the project's cash flows. If the IRR exceeds the discount rate (DR), the project should be approved. If the IRR is less than the cost of capital, the project should be rejected. Prior to the widespread availability of spreadsheet and finance application software, the IRR would be computed by trial and error by guessing at the IRR and recomputing until NPV = 0.

The project in the example in Table 20.2 has an IRR of 19.9%, which is above the 10% discount rate used for the project. Note that IRR and NPV are consistent decision criteria, using estimated cash flows and the discount rate as key inputs. The use of IRR and NPV will result in consistent decisions as follows:

TABLE 20.2 IRR Illustration image

Internal Rate of Return
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6
Project Cash Flows:
Cash Inflows −24,000 8,000 8,000 8,000 8,000 8,000
Present Value Factor 0.83 0.70 0.58 0.48 0.40 0.34
Present Value −20,024 5,569 4,646 3,876 3,234 2,698
Sum PV 0
NPV 0
IRR 19.9%
IRR NPV Result
IRR > DR NPV > 0 Approve
IRR < DR NPV < 0 Reject

Payback

The investment payback is a simple measure that estimates how long (in years and fractions of years) it will take to recover the investment in a project. Investments with shorter payback periods are typically viewed as positive; investments with longer payback periods may be rejected or require additional review. This method does not consider the time value of money (that is, cash flow in future years does not have the same value as an equivalent cash amount now). Despite this criticism, it has high acceptance and usage because it is easily understood and measures an important characteristic: How long until we recover our initial investment? Many organizations have rules of thumb based on payback, requiring a certain class of investments to have a payback of three years or less.

In this example, the cumulative cash flow for the project becomes positive in year 3. We estimate the payback as shown in Table 20.3.

TABLE 20.3 Payback Illustration image

Payback
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6
Project Cash Flows:
Cash Inflows 8,000 8,000 8,000 8,000 8,000
Cash Outflow −24,000
Cumulative −24,000 −16,000 −8,000 8,000 16,000
Payback 3.0

Typically, the payback will not end exactly at the end of a year and will require as estimation of partial‐year payoffs, using interpolation.

All three methods should be utilized, since they each provide different views into the economic dynamics of the project (see Table 20.4).

TABLE 20.4 Combined Illustration image

Discount Rate (10%)
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6
Project Cash Flows:
Cash Flows −24,000 8,000 8,000 8,000 8,000 8,000
Cumulative −24,000 −16,000 −8,000 8,000 16,000
Present Value Factor 0.91 0.83 0.75 0.68 0.62 0.56
Present Value Cash Flow −21,818 6,612 6,011 5,464 4,967 4,516
Net Present Value 5,751
IRR 19.9%
Payback 3.0

While NPV indicates whether the project should be undertaken based on a given discount rate, IRR provides the precise rate of return on the project. By comparing the IRR to the DR, you can get a sense of the return “slack.” Payback complements these measures by estimating the number of years until cash outlays are fully recovered. For example, a project may have a positive NPV and a high rate of return, but the bulk of the cash may be recovered late in the project life, or even in the terminal or salvage value. This long payback should be evaluated in the context of project risks.

We used a discount rate of 10% in the example. The discount rate for each project should be based on the level of risk associated with the project. For practical reasons, companies often set a hurdle rate above the company's cost of capital (covered in Chapter 19) to ensure that projects will earn an acceptable return. If individual projects are perceived as having very low or high risk, the discount rate may be adjusted accordingly, as discussed in Chapter 21.

Other Measures

In addition to NPV, IRR, and payback, the following measures are occasionally used to evaluate capital projects. Their primary utility is to relate the level of NPV to the value of the investment or outflow. This can be useful in ranking projects based on their relative return.

Benefit‐Cost Ratio (BCR). The BCR is computed as follows:

images

For our illustration,

images

Profitability Index (PI). The PI is also used in ranking projects in capital rationing applications. Essentially it scales the NPV of the investment to each dollar of investment. The PI is computed as follows:

images

Step 3: Accept or Reject the Project

Financial theory provides that projects should be approved if the following requirements are met:

  • IRR exceeds the discount rate.
  • NPV is greater than 0.
  • Payback < limit (e.g. 3 years).

Of course, these decision criteria must be applied in a sensible manner. Projects that marginally satisfy these requirements should be subjected to further review, including evaluating the projections and sensitivity and scenario analyses.

What Is a “Strategic Investment”?

Organizations (and most commonly CEOs) often refer to strategic investments as including any investment that is of strategic importance to the enterprise. This may include new products, geographic expansion, or even the acquisition of a firm. Many cynical CFOs jokingly refer to a strategic investment as any investment the CEO is firmly committed to that does not meet the economic criteria described previously! As a result, it is ascribed some unquantifiable “strategic value.”

In some cases, these projects may indeed have dubious value other than as a favorite initiative of the CEO. In other cases, this dichotomy arises because the analysis does not reflect all potential sources of value. The analyst should persevere to identify and estimate other scenarios and options that may not be reflected in the base case of the investment analysis. More on this in Chapter 21.

ILLUSTRATIONS

Two illustrations of capital investment decisions are presented next. The illustrations include the projected cash flows and the evaluation criteria for each investment. Table 20.5 is an example of an analysis of a project to automate manufacturing. Table 20.6 is an illustration of a new product development analysis. These examples were introduced earlier in the chapter to illustrate the identification of incremental cash flows for a project.

In both examples, the shaded part of the worksheet develops the incremental cash flows associated with the project. As discussed earlier in the chapter, each project will have unique characteristics and therefore unique cash flows. In addition to the incremental cash flow per year, we include the cumulative cash flow per year to highlight the timing of cash flows. Note that the cumulative cash flow for the new pharmaceutical remains negative through 2024 (six years) while the cumulative cash flow for the manufacturing project becomes positive in 2021 (three years).

The unshaded portion presents the economic evaluation of each project. In addition to presenting the project NPV, IRR, and payback, we include the present value factor and present value of cash flow for each year. This provides insight into the dynamics of the economic valuation, and the importance of accelerating cash flows in any project.

TABLE 20.5 Capital Expenditure: Manufacturing Project image

Vance Pharma Co. Project Investment Analysis $000's (Unless otherwise noted)
Automate Manufacturing Process
Terminal
Incremental Changes 2018 2019 2020 2021 2022 2023 2024 2025 Value
Revenues
Cost of Revenues
On Incremental Revenues 30%
Project Savings −25,000 −40,000 −75,000 −75,000 −75,000 −75,000 −75,000
Incremental Cost of Revenues −25,000 −40,000 −75,000 −75,000 −75,000 −75,000 −75,000
Gross Margin Impact 25,000 40,000 75,000 75,000 75,000 75,000 75,000
Operating Expenses:
On Incremental Revenues 15%
Project Savings
Project Costs and Expenses 50,000
Depreciation on Project Capital 30,000 30,000 30,000 30,000 30,000
Incremental Operating Expenses 50,000 30,000 30,000 30,000 30,000 30,000
Operating Profit −50,000 −5,000 10,000 45,000 45,000 45,000 75,000 75,000
Tax 40% 20,000 2,000 −4,000 −18,000 −18,000 −18,000 −30,000 −30,000
Operating Profit After Tax −30,000 −3,000 6,000 27,000 27,000 27,000 45,000 45,000
Operating Cash Flow:
Depreciation 30,000 30,000 30,000 30,000 30,000
(Inc) Dec in Accounts Receivable
(Inc) Dec in Inventories 50,000 25,000
Capital Expenditures −150,000
Incremental Cash Flows −180,000 77,000 61,000 57,000 57,000 57,000 45,000 45,000
Cumulative Cash Flow −180,000 −103,000 −42,000 15,000 72,000 129,000 174,000 219,000
Present Value Factor 0.909 0.826 0.751 0.683 0.621 0.564 0.513 0.467
Present Value of Cash Flows −163,636 63,636 45,830 38,932 35,393 32,175 23,092 20,993
NPV $96,414
IRR 28% Discount Rate 10%
Payback 3 years PH Growth Rate 0%

This project has a positive NPV, an IRR that exceeds the discount rate, and a relatively quick payback (3.0 years).

TABLE 20.6 Capital Expenditure: Pharmaceutical Product Development image

Vance Pharma Co. Project Investment Analysis $000's (Unless otherwise noted)
New Treatment for Procrastination
Terminal
Incremental Changes 2018 2019 2020 2021 2022 2023 2024 2025 Value
Revenues 25,000 75,000 125,000 200,000 225,000
Cost of Revenues
On Incremental Revenues 25% 6,250 18,750 31,250 50,000 56,250
Project Savings
Incremental Cost of Revenues 6,250 18,750 31,250 50,000 56,250
Gross Margin Impact 18,750 56,250 93,750 150,000 168,750
Operating Expenses:
On Incremental Revenues 15% 3,750 11,250 18,750 30,000 33,750
Project Savings
Project Costs and Expenses 20,000
Depreciation on Project Capital 10,000 10,000 10,000 10,000 10,000
Incremental Operating Expenses 20,000 10,000 10,000 13,750 21,250 28,750 30,000 33,750
Operating Profit −20,000 −10,000 −10,000 5,000 35,000 65,000 120,000 135,000
Tax 40% 8,000 4,000 4,000 −2,000 −14,000 −26,000 −48,000 −54,000
Operating Profit After Tax −12,000 −6,000 −6,000 3,000 21,000 39,000 72,000 81,000
Operating Cash Flow:
Depreciation 10,000 10,000 10,000 10,000 10,000
(Inc) Dec in Accounts Receivable −938 −2,813 −4,688 −7,500 −8,438
(Inc) Dec in Inventories −1,875 −5,625 −9,375 −15,000 −16,875 −16,875
Capital Expenditures −50,000
Incremental Cash Flows −62,000 4,000 2,125 6,438 18,813 29,313 47,625 55,688 371,250
Cumulative Cash Flows −62,000 −58,000 −55,875 −49,438 −30,625 −1,313 46,313 102,000 473,250
PV Factor 0.870 0.756 0.658 0.572 0.497 0.432 0.376 0.327 0.284
PV Cash Flow −53,913 3,025 1,397 3,681 9,353 12,673 17,904 18,204 105,532
NPV $117,856 Discount Rate 15%
IRR 37% PH Growth Rate 0%
Payback 6 Years

This project has a positive NPV and an IRR that exceeds the discount rate. As expected, the payback (six years) is longer than the manufacturing example, but certainly acceptable for a product development initiative. Note that the discount rate of 15% is higher than that of the manufacturing project due to the higher level or risk (and therefore higher expected return) for developing a new product.

Monitoring Capital Investment Projects

After approving capital investment projects, organizations should have a process for tracking and evaluating the progress and revalidating the continued investment in resources. The critical assumptions and implementation progress can be compared to the original assumptions and project plan in the capital investment proposal (CIP).

This is especially important for mid‐ to long‐term projects such as product development. In these times of rapid change, it is entirely possible that the underlying assumptions for a project have changed to an extent that continued investment is not justified. Have market or competitive factors changed significantly? Will the product meet targeted cost and performance attributes? Similarly, implementation may have incurred delays or unforeseen hurdles that need immediate attention or may threaten the success of the project, including economic justification. Are we on schedule to introduce the product as planned? Will the project meet the expectations for revenue, profits, and NPV that were established in the CIP? By monitoring critical projects, early detection is possible, providing the greatest window for consideration and action. If the ongoing project is determined to be dubious, investments can be terminated and resources redirected to other, more promising opportunities. Venture capital firms are masters of using this method. Their continued investment in a firm or project is dependent on progress or the attainment of specific objectives that foretell ultimate success.

Organizations should also evaluate the performance of completed projects and review utilization of assets on a periodic basis. These topics are covered in Chapter 18, Capital Management and Cash Flow: Long‐Term Assets.

SUMMARY

Capital investment decisions are a critical aspect of managing an enterprise. Each CID requires a determination of whether that project will create value for the owners of the firm. Accordingly, firms must establish a rigorous process to allocate capital and evaluate individual uses of capital.

Capital investments include a wide spectrum of projects and purchases, from purchases of equipment to development of new products to acquiring a company. Common economic evaluation measures include payback, net present value, and internal rate of return.

Since CIDs require projections of future results, they incorporate a significant level of risk and uncertainty. Techniques for identifying and addressing risk and uncertainty are covered in Chapter 21.

..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset