Index

A note on the digital index

A link in an index entry is displayed as the section title in which that entry appears. Because some sections have multiple index markers, it is not unusual for an entry to have several links to the same section. Clicking on any link will take you directly to the place in the text in which the marker appears.

Symbols

100% Complete command (Task tab), Entering a Task’s Completion Percentage
50% Complete command (Task tab), Entering a Task’s Completion Percentage

A

Actions list, Controlling Work When Adding or Removing Resource Assignments
accessing, Controlling Work When Adding or Removing Resource Assignments, Changing Task Types
changing assignment values, Changing Task Types
increasing task durations, Controlling Work When Adding or Removing Resource Assignments
active view
overview, Introducing Project
sorting considerations, Sorting Project Details
View label, Introducing Project
View shortcuts, Introducing Project
Zoom slider, Introducing Project
actual costs, Checking the Project’s Cost and Finish Date, Tracking Actual and Remaining Values for Tasks and Assignments
actual values for tasks
collecting from resources, Tracking Timephased Actual Work for Tasks and Assignments
timephased, Tracking Progress on Tasks and Assignments, Tracking Actual and Remaining Values for Tasks and Assignments
tracking progress, Saving a Project Baseline, Entering a Task’s Completion Percentage, Tracking Progress on Tasks and Assignments, Updating a Baseline
Add Tasks To Timeline dialog box, Customizing the Gantt Chart View
Add To Timeline command (Task tab), Customizing the Timeline View
Advanced Plan Properties dialog box, Checking the Project’s Cost and Finish Date
ALAP constraint type, Setting Task Constraints
All Programs command (Start menu), Copying Views, Saving to Other File Formats from Project
All Subtasks command (View tab), Scheduling Summary Tasks Manually, Examining Task Costs, Consolidating Project Plans
allocations, resource (see )
ASAP constraint type, Setting Task Constraints, Changing Task Types
Assign Resources dialog box
adjusting resource assignments, Controlling Work When Adding or Removing Resource Assignments
assigning cost resources, Assigning Cost Resources to Tasks
assigning material resources, Assigning Material Resources to Tasks
assigning resources to recurring tasks, Setting Up a Recurring Task
assigning work resources, Assigning Work Resources to Tasks, Assigning Work Resources to Tasks, Assigning Cost Resources to Tasks
closing considerations, The Ribbon and Tabs: Finding the Features You Want
depicted, The Ribbon and Tabs: Finding the Features You Want
linking project plans, Linking New Project Plans to a Resource Pool
removing work resources, Controlling Work When Adding or Removing Resource Assignments
Replace button, Examining Resource Allocations over Time
resolving resource overallocations, Examining Resource Allocations over Time
troubleshooting problems, Troubleshooting Time and Schedule Problems, Troubleshooting Cost and Resource Problems
Units field, Examining Resource Allocations over Time
updating assignments in sharer plans, Viewing Assignment Details in a Resource Pool
updating resource pool, Opening a Sharer Plan and Updating a Resource Pool
Assignment group (Format tab)
Information, Delaying the Start of Assignments, Applying Contours to Assignments, Applying Different Cost Rates to Assignments
Notes button, Applying Contours to Assignments
Assignment Information dialog box
accessing, Delaying the Start of Assignments
applying contours, Applying Contours to Assignments
applying different cost rates, Applying Different Cost Rates to Assignments
delaying start of assignments, Delaying the Start of Assignments
resolving resource overallocations, Examining Resource Allocations over Time
Units field, Examining Resource Allocations over Time
updating actual work values, Tracking Actual and Remaining Values for Tasks and Assignments
assignment notes
defined, Checking the Plan’s Duration
pasting graphic images, Copying Project Data to Other Programs
resource notes and, Applying Contours to Assignments
Assignment Reports dialog box, Customizing and Printing Reports
assignment units, Adjusting Working Time for Individual Tasks
assignments (see )
Assignments group (Resource tab)
Assign Resources, The Ribbon and Tabs: Finding the Features You Want, Assigning Work Resources to Tasks, Setting Up a Recurring Task, Assigning Material Resources to Tasks, Troubleshooting Time and Schedule Problems, Viewing Assignment Details in a Resource Pool, Opening a Sharer Plan and Updating a Resource Pool
Resource Pool, Creating a Resource Pool, Linking New Project Plans to a Resource Pool, Opening a Sharer Plan and Updating a Resource Pool
Auto Schedule command (Task tab), Switching Task Scheduling from Manual to Automatic
AutoFilters
accessing, Sorting Project Details
applying, Filtering Project Details
functionality, Filtering Project Details
troubleshooting problems and, Troubleshooting Cost and Resource Problems

B

Background Color button, Customizing the Gantt Chart View, Formatting a Timeline View
Backstage view
displaying, The Backstage: Managing Files and Setting Options, Documenting Tasks and the Project Plan
Help pane, Troubleshooting Scope-of-Work Problems
managing files, Introducing Project
Print Preview option, Printing Views, Printing Views: Advanced Options, Printing Reports: Advanced Options
project summary tasks, Customizing the Gantt Chart View
setting options, Introducing Project
Bar Styles dialog box
accessing, The Ribbon and Tabs: Finding the Features You Want, Formatting a Gantt Chart View
formatting Calendar view, Formatting a Calendar View
formatting Gantt bars, Customizing the Gantt Chart View, Formatting a Gantt Chart View
Bar Styles group (Format tab)
Critical Tasks check box, Viewing the Project’s Critical Path
Format, Customizing the Gantt Chart View
Slack check box, Viewing the Project’s Critical Path
base calendars
creating, Adjusting Working Time for Individual Tasks
defined, Setting Nonworking Days
Standard, Adjusting Working Time for Individual Resources, Adjusting Working Time for Individual Tasks
updating working times in resource pools, Updating All Plans’ Working Times in a Resource Pool
baseline costs, Checking the Project’s Cost and Finish Date
baseline plans
baseline costs, Checking the Project’s Cost and Finish Date
cautions overwriting values, Updating a Baseline
for projects, Tracking Progress on Tasks
purpose, Tracking Progress on Tasks and Assignments
saving interim plans, Updating a Baseline
updating, Tracking Progress on Tasks and Assignments
bottom-up planning, Organizing Tasks into Phases
Box command, Formatting a Network Diagram View
Box Styles dialog box, Formatting a Network Diagram View, Formatting a Network Diagram View
Browse dialog box, Recording Macros
Budget Cost report, Examining Task Costs

C

Calendar tab (Tools menu), Setting Up a Recurring Task
Calendar view
filtering support, Filtering Project Details
formatting, Formatting a Network Diagram View
functionality, The Ribbon and Tabs: Finding the Features You Want
calendars (see specific types of calendars)
callouts, displaying tasks as, Customizing the Timeline View
Change Working Time dialog box
Create New Calendar option, Adjusting Working Time for Individual Tasks
creating working time exception, Setting Nonworking Days
Exceptions tab, Adjusting Working Time for Individual Resources
specifying working/nonworking times, Adjusting Working Time for Individual Resources
updating resource information, Updating a Resource’s Information in a Resource Pool
updating working times, Updating All Plans’ Working Times in a Resource Pool
Work Weeks tab, Adjusting Working Time for Individual Resources, Adjusting Working Time for Individual Tasks
Clipboard group (Task tab)
Copy, Copying Project Data to Other Programs, Copying Project Data to Other Programs
Copy Picture dialog box, Copying Views, Identifying Tasks that Have Slipped, Recording Macros
functionality, The Ribbon and Tabs: Finding the Features You Want
Close command (File tab), The Backstage: Managing Files and Setting Options
colors
adjusting for Gantt bars, Customizing the Gantt Chart View
adjusting for milestones, Customizing the Gantt Chart View, Customizing the Gantt Chart View
changing for task bars, Formatting a Timeline View
formatting Timeline view, Formatting a Timeline View
predefined styles, The Ribbon and Tabs: Finding the Features You Want, Customizing the Gantt Chart View
Columns group (Format tab)
Custom Fields, Examining Resource Costs
Insert Column, Customizing Tables
columns, manipulating in tables, Customizing Tables
commands, defined, Introducing Project
confirmation messages, Recording Macros
consolidating project plans, Consolidating Project Plans
constraints
categories of, Adjusting Task Relationships
entering deadline dates, Changing Task Types
removing, Setting Task Constraints
setting for tasks, Adjusting Task Relationships
types of, Setting Task Constraints
consumption rates, Assigning Material Resources to Tasks
contours, applying to resource assignments, Delaying the Start of Assignments
Copy command (Task tab), Copying Project Data to Other Programs, Copying Project Data to Other Programs
Copy group (Format tab), Copying Views
Copy Picture dialog box
copying views, Copying Views
recording macros, Recording Macros
reporting project status, Identifying Tasks that Have Slipped
Copy Timeline command (Format tab), Copying Views
copying
data to other programs, Copying Project Data to Other Programs
GIF image files, Copying Views
views, Drawing on a Gantt Chart
cost rates, changing, Applying Contours to Assignments
cost resources
accruing to project costs, Entering Fixed Costs
assigning to tasks, Controlling Work When Adding or Removing Resource Assignments
costs incurred with, Controlling Work When Adding or Removing Resource Assignments
defined, Setting Up Resources
getting information, Entering Resource Pay Rates
setting up, Setting Up Cost Resources
Cost table
accessing, Entering Actual Values for Tasks, Entering Fixed Costs, Applying Contours to Assignments, Checking the Project’s Cost and Finish Date
copying project data, Copying Project Data to Other Programs
entering actual costs manually, Tracking Actual and Remaining Values for Tasks and Assignments
examining resource costs, Examining Task Costs
examining task costs, Examining Task Costs
reporting project cost variance, Reporting Project Cost Variance with a Stoplight View
troubleshooting problems, Troubleshooting Time and Schedule Problems, Troubleshooting Scope-of-Work Problems
costs, project (see )
Create New Base Calendar dialog box, Adjusting Working Time for Individual Tasks
critical path
defined, Setting Up a Recurring Task, Checking the Project’s Cost and Finish Date
highlighting, Troubleshooting Time and Schedule Problems
project finish date and, Checking the Project’s Cost and Finish Date
viewing, Setting Up a Recurring Task
Critical Task filter, Filtering Project Details
Ctrl+F key combination, Recording Macros
Ctrl+G key combination, Changing Task Types, Troubleshooting Time and Schedule Problems, Recording Macros
current costs, Checking the Project’s Cost and Finish Date
Current Selection group (Format tab), Customizing the Timeline View
Custom AutoFilter dialog box, Filtering Project Details
Custom Fields dialog box, Examining Resource Costs
custom fields, creating, Customizing Tables
Custom Reports dialog box, Printing Views: Advanced Options, Printing Reports: Advanced Options
Custom tab, Customizing the Ribbon and Quick Access Toolbar
customizing
filters, Filtering Project Details, Filtering Project Details
Gantt Chart view, Formatting and Sharing Your Plan
Max. Units values, Setting Up Resource Availability to Apply at Different Times
Quick Access toolbar, Editing Macros
reports, Printing Views
ribbon interface, Editing Macros
tables, Filtering Project Details
Timeline view, Customizing the Gantt Chart View
views, Customizing Tables, Sharing Custom Elements Between Project Plans

D

Data group (View tab), Identifying Tasks that Have Slipped
(see also , )
Group By button, Sorting Project Details, Grouping Project Details
Highlight, Troubleshooting Time and Schedule Problems, Troubleshooting Time and Schedule Problems
Outline, Scheduling Summary Tasks Manually, Viewing Resource Capacity, Examining Resource Allocations over Time, Examining Task Costs, Consolidating Project Plans
Sort, The Ribbon and Tabs: Finding the Features You Want, Sorting Project Details, Examining Resource Costs
data maps, Opening Other File Formats in Project
Data Template Definition dialog box, Formatting a Network Diagram View
Data Templates dialog box, Formatting a Network Diagram View
deadline dates, Changing Task Types, Troubleshooting Time and Schedule Problems
dedicated resource pools, Creating a Resource Pool
Define Group Interval dialog box, Grouping Project Details
Define New View dialog box, Customizing Views
deliverables
defined, A Short Course in Project Management
defining tasks for, Entering Task Names
Detail Gantt view
accessing, Viewing the Project’s Critical Path
free slack in, Viewing the Project’s Critical Path
Gantt Chart view and, Applying Advanced Formatting and Printing
viewing critical path, Viewing the Project’s Critical Path
viewing tasks with variance, Identifying Tasks that Have Slipped
Details button (Resource tab), Documenting Resources, Documenting Resources
Details command (View tab)
accessing Task Form, Assigning Work Resources to Tasks
functionality, Views: Working with Schedule Details the Way You Want
viewing assignments in resource pools, Viewing Assignment Details in a Resource Pool
Details dialog box, Adjusting Working Time for Individual Tasks
Details group (Format tab)
Actual Work, Tracking Actual and Remaining Values for Tasks and Assignments
Add Details, Tracking Actual and Remaining Values for Tasks and Assignments, Examining Resource Costs
Baseline Work, Examining Task Costs
displaying work values, Examining Resource Allocations over Time
Notes, Documenting Resources
Remaining Availability check box, Viewing Resource Capacity
Work check box, Viewing Resource Capacity, Troubleshooting Time and Schedule Problems
Details Styles dialog box, Examining Resource Costs
Display As Callout command (Format tab), Customizing the Timeline View
Document Export Options dialog box, Printing Views: Advanced Options
documentation
copying views for, Drawing on a Gantt Chart
for project plans, Checking the Plan’s Duration
for tasks, Checking the Plan’s Duration
Drawing command (Format tab)
accessing, Drawing on a Gantt Chart
functionality, Customizing the Timeline View
Properties, Drawing on a Gantt Chart
Text Box, Drawing on a Gantt Chart
Drawings group (Format tab), Drawing on a Gantt Chart
durations, Tracking Timephased Actual Work for Tasks and Assignments
(see also )
abbreviating, Entering Durations
accurate, Entering Durations
assigning overtime hours, Troubleshooting Time and Schedule Problems
checking, Setting Nonworking Days
critical path and, Setting Up a Recurring Task
entering, Entering Durations
in project triangle model, Getting Your Project Back on Track, The Project Triangle: Viewing Projects in Terms of Time, Cost, and Scope
increasing for tasks, Controlling Work When Adding or Removing Resource Assignments
managing project constraints, Scope
recurring tasks, Setting Up a Recurring Task
summary tasks, Entering a Milestone, Scheduling Summary Tasks Manually
task scheduling formula, Assigning Work Resources to Tasks, Adjusting Working Time for Individual Tasks
troubleshooting problems, Getting Your Project Back on Track

E

e-mail messages, copying views for, Drawing on a Gantt Chart
Editing group (Task tab), Customizing the Gantt Chart View, Copying Views, Adjusting Task Relationships
editing macros, Recording Macros
Enterprise Project Management (EPM), A Guided Tour of Project, Changing Account Settings if Connected to Project Server
Entire Project command (View tab)
consolidating project plans, Consolidating Project Plans
scheduling summary tasks, Scheduling Summary Tasks Manually
viewing critical path, Viewing the Project’s Critical Path, Leveling Overallocated Resources
entry bar (formula bar), Introducing Project
Entry table
accessing, Filtering Project Details
as default, Sorting Project Details
copying project data, Copying Project Data to Other Programs
modifying, Filtering Project Details
task ID numbers, Linking Tasks
viewing project tasks, Printing Reports: Advanced Options
EPM (see )
equipment resources, setting up, Setting Up Work Resources
Excel worksheets (see )
Existing Tasks command (Format tab), Customizing the Gantt Chart View
Exit command (File tab), The Backstage: Managing Files and Setting Options
export maps, Opening Other File Formats in Project, Opening Other File Formats in Project
Export Wizard, Saving to Other File Formats from Project

F

FF task relationship (see )
fields, creating custom, Customizing Tables
file formats
from previous versions, Saving to Other File Formats from Project
legacy files, Saving to Other File Formats from Project
opening other, Opening Other File Formats in Project
saving to other, Opening Other File Formats in Project
task lists in other, Opening Other File Formats in Project
File tab, Customizing Views
(see also )
Close, The Backstage: Managing Files and Setting Options
displaying Backstage view, The Backstage: Managing Files and Setting Options, Documenting Tasks and the Project Plan
Exit, The Backstage: Managing Files and Setting Options
Help, The Backstage: Managing Files and Setting Options
Info, The Backstage: Managing Files and Setting Options, Sharing Custom Elements Between Project Plans
New, Introducing Project, Creating a New Project Plan, Creating a Resource Pool
Open, Introducing Project, Creating a Resource Pool
Print, The Backstage: Managing Files and Setting Options, Printing Views
Recent, The Backstage: Managing Files and Setting Options
Save, Introducing Project
Save & Send, The Backstage: Managing Files and Setting Options, Printing Views: Advanced Options
Save As, The Backstage: Managing Files and Setting Options, The Backstage: Managing Files and Setting Options, Customizing the Gantt Chart View, Identifying Tasks that Have Slipped
files
managing, Introducing Project
opening, The Backstage: Managing Files and Setting Options
Filter button (View tab)
Clear Filter, Identifying Tasks that Have Slipped, Examining Task Costs
Display AutoFilter, Sorting Project Details
functionality, Filtering Project Details, Identifying Tasks that Have Slipped
Incomplete Tasks, Troubleshooting Scope-of-Work Problems
Late Tasks, Identifying Tasks that Have Slipped
More Filters dialog box, Filtering Project Details, Identifying Tasks that Have Slipped, Identifying Tasks that Have Slipped, Examining Task Costs
Slipped/Late Progress, Identifying Tasks that Have Slipped
Slipping Tasks, Identifying Tasks that Have Slipped
Filter Definition dialog box, Filtering Project Details
filter indicator, Filtering Project Details
filtering
for delayed/slipping tasks, Identifying Tasks that Have Slipped
global templates and, Sharing Custom Elements Between Project Plans
project details, Grouping Project Details
visual reports, Generating Visual Reports with Excel and Visio
finish date, project, Checking the Project’s Cost and Finish Date, Troubleshooting Time and Schedule Problems
Finish No Earlier Than (FNET) constraint type, Setting Task Constraints
Finish No Later Than (FNLT) constraint type, Setting Task Constraints
finish-to-finish (FF) task relationship, Linking Tasks, Adjusting Task Relationships
finish-to-start (FS) task relationship, Linking Tasks, Adjusting Task Relationships
fixed consumption rates, Assigning Material Resources to Tasks
fixed costs
assigning to tasks, Entering Fixed Costs
defined, Entering Fixed Costs
determining accrual methods, Entering Fixed Costs
examples of, Entering Fixed Costs
fixed-duration task type, Adjusting Working Time for Individual Tasks, Applying Contours to Assignments
fixed-unit task type
as default, Adjusting Working Time for Individual Tasks
assigning material resources, Assigning Material Resources to Tasks
defined, Controlling Work When Adding or Removing Resource Assignments
fixed-work task type, Adjusting Working Time for Individual Tasks
float (slack), Viewing the Project’s Critical Path
Fluent user interface (see )
FNET constraint type (see )
FNLT constraint type (see )
Font Color button, Formatting a Timeline View
Font group (Format tab)
Background Color button, Formatting a Timeline View
Font Color button, Formatting a Timeline View
Italic, Formatting a Timeline View
Font group (Task tab), The Ribbon and Tabs: Finding the Features You Want
Format Bar dialog box, Customizing the Gantt Chart View
Format Bar Styles button (Format tab), The Ribbon and Tabs: Finding the Features You Want
Format Drawing dialog box, Drawing on a Gantt Chart
Format group (Format tab)
Bar Styles, Formatting a Calendar View
Box Styles, Formatting a Network Diagram View
Gridlines, Customizing the Gantt Chart View, Formatting a Gantt Chart View
Layout, Interrupting Work on a Task, Formatting a Gantt Chart View
Text Styles button, Formatting a Gantt Chart View
Format tab, Tracking Actual and Remaining Values for Tasks and Assignments
(see also , )
Assignment group, Delaying the Start of Assignments, Applying Contours to Assignments, Applying Contours to Assignments, Applying Different Cost Rates to Assignments
Bar Styles group, Customizing the Gantt Chart View, Viewing the Project’s Critical Path
Columns group, Customizing Tables, Examining Resource Costs
Current Selection group, Customizing the Timeline View
Drawings group, Drawing on a Gantt Chart
Font group, Formatting a Timeline View
functionality, The Ribbon and Tabs: Finding the Features You Want
Gantt Chart Style group, The Ribbon and Tabs: Finding the Features You Want, Customizing the Gantt Chart View
Insert group, Customizing the Gantt Chart View
label changes, Views: Working with Schedule Details the Way You Want
Show/Hide group, Customizing the Gantt Chart View, Consolidating Project Plans
Text group, Formatting a Gantt Chart View
formatting
Calendar view, Formatting a Network Diagram View
Gantt Chart view, Customizing the Gantt Chart View, Applying Advanced Formatting and Printing
Network Diagram view, Formatting a Timeline View
task names visually, Customizing the Gantt Chart View
Timeline view, Formatting a Gantt Chart View
Tracking Gantt view, Applying Advanced Formatting and Printing
formula bar (entry bar), Introducing Project
Formula dialog box, Reporting Project Cost Variance with a Stoplight View
free slack, Viewing the Project’s Critical Path
FS task relationship (see )

G

Gantt bars
attaching text boxes to, Drawing on a Gantt Chart
customizing Gantt Chart view, Formatting and Sharing Your Plan
defined, Formatting and Sharing Your Plan
for recurring tasks, Setting Up a Recurring Task
for summary tasks, Scheduling Summary Tasks Manually
identifying task slippage, Identifying Tasks that Have Slipped
nonworking time and, Entering a Task’s Completion Percentage
scrolling to tasks, Customizing the Gantt Chart View
Gantt Chart Style group (Format tab)
Format Bar Styles button, The Ribbon and Tabs: Finding the Features You Want
More button, The Ribbon and Tabs: Finding the Features You Want, Customizing the Gantt Chart View
Gantt Chart view
accessing, Saving a Project Baseline, Setting Up a Recurring Task, Viewing the Project’s Critical Path
adjusting resource assignments, Controlling Work When Adding or Removing Resource Assignments
applying Schedule table, Viewing the Project’s Critical Path
as default view, Formatting and Sharing Your Plan
assigning material resources, Assigning Material Resources to Tasks
assigning work resources, Assigning Work Resources to Tasks, Assigning Work Resources to Tasks
changing task default settings, Controlling Work When Adding or Removing Resource Assignments
changing timescale, Customizing the Timeline View
components, Formatting and Sharing Your Plan
copying, Drawing on a Gantt Chart
copying project data, Copying Project Data to Other Programs
creating project dependencies, Creating Dependencies Between Projects
customizing, Formatting and Sharing Your Plan
deadline indicators, Entering Deadline Dates
depicted, Views: Working with Schedule Details the Way You Want
drawing considerations, Customizing the Timeline View
filtering project details, Filtering Project Details
formatting, Customizing the Gantt Chart View, Applying Advanced Formatting and Printing
Gantt bars, Formatting and Sharing Your Plan
highlighting critical path, Troubleshooting Time and Schedule Problems
orange vertical line, Creating a New Project Plan
overview, The Ribbon and Tabs: Finding the Features You Want, Applying Advanced Formatting and Printing
pan and zoom controls, Customizing the Timeline View
pasting graphic images, Copying Project Data to Other Programs
Print Preview option, Printing Views
printing, Copying Views
printing options, Printing Views: Advanced Options
project summary tasks, Customizing the Gantt Chart View
recording macros, Recording Macros
rescheduling incomplete work, Rescheduling Incomplete Work
ScreenTips in, Examining Resource Allocations over Time, Updating a Baseline
scrolling, Customizing the Timeline View
sharing custom elements, Sharing Custom Elements Between Project Plans
splitting tasks, Applying Contours to Assignments
task relationships, Linking Tasks, Linking Tasks
task scheduling and, Creating a New Project Plan
troubleshooting problems, Troubleshooting Time and Schedule Problems, Troubleshooting Cost and Resource Problems
updating assignments in sharer plans, Viewing Assignment Details in a Resource Pool
viewing project tasks, Printing Reports: Advanced Options
viewing resource names, Setting Up Work Resources
Gantt Chart with Timeline view, The Ribbon and Tabs: Finding the Features You Want, Formatting and Sharing Your Plan, Printing Reports: Advanced Options
GIF image files
copying, Copying Views
editing macros, Recording Macros, Editing Macros
macro names, Recording Macros
recording macros, Recording Macros
global templates
defined, Sharing Custom Elements Between Project Plans
elements supported, Sharing Custom Elements Between Project Plans
project plans and, Sharing Custom Elements Between Project Plans
storing macros, Recording Macros
Go To command/dialog box
adding to Quick Access toolbar, Customizing the Ribbon and Quick Access Toolbar
shortcut keys and, Changing Task Types, Troubleshooting Time and Schedule Problems, Recording Macros
Gridlines command (Format tab), Customizing the Gantt Chart View, Formatting a Gantt Chart View
Group Definition dialog box, Grouping Project Details
grouping project details, Sorting Project Details
groups (ribbon interface), Introducing Project, Sharing Custom Elements Between Project Plans

M

macros
editing, Recording Macros
naming conventions, Recording Macros
recording, Sharing Custom Elements Between Project Plans
security considerations, Recording Macros
storing, Recording Macros
Macros dialog box, Recording Macros, Editing Macros, Editing Macros
Macros group (View tab)
Macros dialog box, Recording Macros, Editing Macros, Editing Macros
Record Macro dialog box, Recording Macros
Stop Recording, Recording Macros
manually scheduling tasks, Entering Durations
maps, import/export, Opening Other File Formats in Project, Opening Other File Formats in Project
Mark On Track button (Task tab), Entering Actual Values for Tasks
master projects, defined, Consolidating Project Plans
material resources
assigning to tasks, Assigning Material Resources to Tasks
defined, Setting Up Resources, Setting Up Material Resources
setting up, Setting Up Material Resources
variable consumption rates, Assigning Material Resources to Tasks
Max. Units field
examing resource allocations, Fine-Tuning the Project Plan
functionality, Setting Up Work Resources, Assigning Resources to Tasks, Fine-Tuning Resource Details, Setting Up Resource Availability to Apply at Different Times
resource calendars and, Adjusting Working Time for Individual Resources
MCTS (see )
menus, tabs as replacements, Introducing Project
MFO constraint type (see )
Microsoft Certified Technology Specialist (MCTS), Joining a Project Learning Community
Microsoft Excel
as editable format, Identifying Tasks that Have Slipped
AutoFill handle, Applying Contours to Assignments
AutoFilters, Filtering Project Details
copying project data to, Copying Project Data to Other Programs
generating visual reports, Saving to Other File Formats from Project
opening file format from, Opening Other File Formats in Project
Paste Special feature, Copying Project Data to Other Programs
PivotChart feature, Generating Visual Reports with Excel and Visio
PivotTable feature, Generating Visual Reports with Excel and Visio, Generating Visual Reports with Excel and Visio
Resource Cost Summary report, Examining Resource Costs
saving supported formats, Opening Other File Formats in Project
Microsoft Project 2010 (see )
Microsoft Project Document Object, Copying Project Data to Other Programs
Microsoft Project Server, Using the Practice Files if Connected to Project Server
Microsoft Project User Group (MPUG), Joining a Project Learning Community
Microsoft SharePoint, synchronizing task lists, Generating Visual Reports with Excel and Visio
Microsoft Visual Basic for Applications (VBA), Sharing Custom Elements Between Project Plans, Recording Macros
Microsoft Word, Copying Project Data to Other Programs
Milestone command (Task tab), Entering Durations
milestones
adding to Timeline view, Customizing the Timeline View
adjusting colors, Customizing the Gantt Chart View, Customizing the Gantt Chart View
defined, Entering Durations
entering, Entering Durations
formatting indicator, Customizing the Gantt Chart View
marking tasks as, Entering a Milestone
on Gantt charts, Formatting and Sharing Your Plan
mini-toolbars, Introducing Project, Customizing the Gantt Chart View
Mode command (Task tab), Switching Task Scheduling from Manual to Automatic
More button (Format tab), The Ribbon and Tabs: Finding the Features You Want, Customizing the Gantt Chart View
More Filters dialog box
Cost Overbudget, Examining Task Costs
functionality, Filtering Project Details, Identifying Tasks that Have Slipped
Late/Overbudget Tasks Assigned To, Examining Task Costs
Slipping Tasks, Identifying Tasks that Have Slipped
More Groups dialog box, Grouping Project Details
More Tables dialog box, Filtering Project Details
More Views dialog box, Leveling Overallocated Resources, Customizing Views
MPUG (see )
MSO constraint type (see )
Multiple Baselines Gantt view, Applying Advanced Formatting and Printing
Must Finish On (MFO) constraint type, Setting Task Constraints, Changing Task Types
Must Start On (MSO) constraint type
cautions using, Setting Task Constraints
defined, Setting Task Constraints
negative slack and, Setting Task Constraints
My Commands group (Custom tab), Customizing the Ribbon and Quick Access Toolbar

N

naming conventions
for macros, Recording Macros
for resource pools, Creating a Resource Pool
navigating in Gantt Chart view, Customizing the Timeline View
negative slack, Setting Task Constraints
Network Diagram view
filtering support, Filtering Project Details
formatting, Formatting a Timeline View
functionality, Formatting a Timeline View
task relationships, Linking Tasks
New command (File tab)
creating project plans, Creating a New Project Plan, Creating a Resource Pool
functionality, Introducing Project
New Window command (View tab), The Ribbon and Tabs: Finding the Features You Want, Consolidating Project Plans
nonworking days, Setting Nonworking Days, Entering a Task’s Completion Percentage
Notepad, Copying Project Data to Other Programs, Saving to Other File Formats from Project
notes (see specific types of notes)

O

OLAP (see )
OLE objects, Copying Project Data to Other Programs
ongoing operations, defined, A Short Course in Project Management
Online Analytical Processing (OLAP), Generating Visual Reports with Excel and Visio
Open command (File tab)
creating resource pools, Creating a Resource Pool
functionality, Introducing Project
opening
files, The Backstage: Managing Files and Setting Options
other file formats, Opening Other File Formats in Project
resource pools, Updating a Resource’s Information in a Resource Pool, Linking New Project Plans to a Resource Pool
sharer plans, Linking New Project Plans to a Resource Pool
Options command (File tab) (see )
Organizer feature
accessing, Sharing Custom Elements Between Project Plans
Calendars tab, Sharing Custom Elements Between Project Plans
depicted, Sharing Custom Elements Between Project Plans
functionality, Sharing Custom Elements Between Project Plans
Outline command (View tab)
All Subtasks, Scheduling Summary Tasks Manually, Examining Task Costs, Consolidating Project Plans
Hide Subtasks, Viewing Resource Capacity, Examining Resource Allocations over Time
Outline Level 1, Scheduling Summary Tasks Manually, Examining Task Costs
overallocations (resources)
defined, Examining Resource Allocations over Time
evaluating, Examining Resource Allocations over Time
resolving, Examining Resource Allocations over Time
Overbudget Resources report, Examining Resource Costs
Overbudget Tasks report, Examining Task Costs
overtime hours, assigning, Troubleshooting Time and Schedule Problems
OvertimeRate field, Entering Resource Pay Rates
Overview Reports dialog box, Customizing and Printing Reports

P

Page Setup dialog box, Printing Views, Customizing and Printing Reports, Printing Views: Advanced Options
pan controls, Customizing the Timeline View
passwords, setting, Entering Resource Pay Rates
Paste Special feature, Copying Project Data to Other Programs
pasting data (see )
pay rates
applying at different times, Entering Multiple Pay Rates for a Resource
multiple, Entering Multiple Pay Rates for a Resource
PDF format, Identifying Tasks that Have Slipped, Printing Views: Advanced Options
peak units, Adjusting Working Time for Individual Tasks
people resources (see )
phases, Customizing the Timeline View
(see also )
bottom-up planning, Organizing Tasks into Phases
defined, Organizing Tasks into Phases
organizing tasks into, Entering a Milestone
top-down planning, Organizing Tasks into Phases
pivot diagrams, Formatting a Network Diagram View
Planning Wizard, Troubleshooting Scope-of-Work Problems
PMI (see )
predecessor tasks, Organizing Tasks into Phases, Adjusting Task Relationships
presentations, copying views for, Drawing on a Gantt Chart
Print command (File tab), The Backstage: Managing Files and Setting Options, Printing Views
Print Preview window
Backstage view, Printing Views, Printing Views: Advanced Options, Printing Reports: Advanced Options
Gantt Chart view, Printing Views
Multiple Pages option, Printing Views, Printing Views
Page Right option, Printing Views
Page Setup option, Printing Views
Print Specific Dates option, Printing Views
Settings option, Printing Views
Timeline view, Printing Views
viewing reports, Printing Views
zoom controls, Printing Views: Advanced Options
printing
reports, Printing Views, Printing Views: Advanced Options
views, Copying Views, Printing Views: Advanced Options
product scope, defined, Entering Task Names
Project 2010
active view, Introducing Project
editions supported, A Guided Tour of Project
interface components, Introducing Project
starting, A Guided Tour of Project
project baseline, saving, Tracking Progress on Tasks
project calendars, Adjusting Working Time for Individual Tasks
(see also )
functionality, Setting Nonworking Days
global templates and, Sharing Custom Elements Between Project Plans
project costs
checking, Checking the Project’s Cost and Finish Date
examining resource costs, Examining Task Costs
examining task costs, Examining Task Costs
in project triangle model, Getting Your Project Back on Track, Cost
managing project constraints, Scope
reporting variance in, Examining Resource Costs
troubleshooting problems, Troubleshooting Time and Schedule Problems
project dependencies, creating, Consolidating Project Plans
project details
filtering, Grouping Project Details
grouping, Sorting Project Details
sorting, Sorting Project Details
project duration (see )
project finish date, Checking the Project’s Cost and Finish Date, Troubleshooting Time and Schedule Problems
Project Information dialog box
checking plan duration, Setting Nonworking Days
checking project finish dates, Checking the Project’s Cost and Finish Date
creating project plans, Creating a New Project Plan
depicted, Checking the Project’s Cost and Finish Date
identifying task slippage, Identifying Tasks that Have Slipped
troubleshooting problems, Troubleshooting Time and Schedule Problems
viewing statistics, Assigning Resources to Tasks, Assigning Cost Resources to Tasks
Project learning communities, Roadmap for Developing Your Project and Project Management Skills
Project Management Institute (PMI), Joining a Project Management Learning Community
Project Options dialog box
accessing, Customizing Views
applying pay rates automatically, Entering Resource Pay Rates
breaking task/assignment relationships, Tracking Timephased Actual Work for Tasks and Assignments
changing default view, Formatting and Sharing Your Plan
cross-project links, Creating Dependencies Between Projects
Customize Ribbon tab, Customizing the Ribbon and Quick Access Toolbar
default start/end dates, Setting Task Constraints
displaying entry bar, Introducing Project
entering actual costs manually, Tracking Actual and Remaining Values for Tasks and Assignments
functionality, The Backstage: Managing Files and Setting Options
grouping project details, Grouping Project Details
honoring relationships over constraints, Setting Task Constraints
identifying tasks on critical path, Viewing the Project’s Critical Path
Quick Access Toolbar tab, Editing Macros
rescheduling incomplete work, Rescheduling Incomplete Work
Trust Center dialog box, Opening Other File Formats in Project, Saving to Other File Formats from Project
Work Is Entered In box, Tracking Timephased Actual Work for Tasks and Assignments
project plans
assigning resources, Assigning Resources to Tasks
automating task scheduling, Switching Task Scheduling from Manual to Automatic
breaking link with resource pools, Creating a Resource Pool
checking cost/finish date, Checking the Project’s Cost and Finish Date
checking duration, Setting Nonworking Days
consolidating, Consolidating Project Plans
copying views, Drawing on a Gantt Chart
creating, Creating a Task List, Creating a Resource Pool
customizing Gantt Chart view, Formatting and Sharing Your Plan
customizing reports, Printing Views
customizing Timeline view, Customizing the Gantt Chart View
data considerations, Formatting and Sharing Your Plan
documenting, Checking the Plan’s Duration
drawing on Gantt charts, Customizing the Timeline View
entering durations, Entering Durations
entering milestones, Entering Durations
entering task names, Creating a New Project Plan
evaluating resource allocations, Examining Resource Allocations over Time
examining resource allocations, Fine-Tuning the Project Plan
Gantt charts and, Formatting and Sharing Your Plan
global templates and, Sharing Custom Elements Between Project Plans
leveling resource allocations, Interrupting Work on a Task, Examining Resource Allocations over Time, Resolving Resource Overallocations Manually
linking tasks, Organizing Tasks into Phases
linking to resource pools, Updating All Plans’ Working Times in a Resource Pool
organizing tasks into phases, Entering a Milestone
printing reports, Printing Views
printing views, Copying Views
resolving overallocations, Examining Resource Allocations over Time
saving project baselines, Saving a Project Baseline
setting nonworking days, Setting Nonworking Days
sharing custom elements, Sharing Custom Elements Between Project Plans
storing macros, Recording Macros
updating baselines, Updating a Baseline
viewing resource capacity, Assigning Material Resources to Tasks
project scope
defined, Entering Task Names
in project triangle model, Getting Your Project Back on Track, Cost
managing project constraints, Scope
task durations and, Entering Durations
troubleshooting problems, Troubleshooting Cost and Resource Problems
viewing resource capacity, Assigning Material Resources to Tasks
Project Server, Using the Practice Files if Connected to Project Server
Project Statistics dialog box, Checking the Plan’s Duration, Identifying Tasks that Have Slipped
project status
examining resource costs, Examining Task Costs
examining task costs, Examining Task Costs
identifying task slippage, Viewing and Reporting Project Status
identifying variance, Identifying Tasks that Have Slipped
reporting, Identifying Tasks that Have Slipped
reporting variance in project costs, Examining Resource Costs
Project Summary Task (Format tab), Customizing the Gantt Chart View, Consolidating Project Plans
Project tab, Setting Nonworking Days
(see also , )
functionality, The Ribbon and Tabs: Finding the Features You Want
Insert group, Consolidating Project Plans
Schedule group, Saving a Project Baseline, Updating a Baseline
Status group, Saving a Project Baseline, Rescheduling Incomplete Work
project tracking
actual values for tasks/assignments, Saving a Project Baseline, Entering a Task’s Completion Percentage, Updating a Baseline
as scheduled, Saving a Project Baseline
completion percentage for tasks, Saving a Project Baseline, Tracking a Project as Scheduled
considerations, Tracking Progress on Tasks
remaining values for tasks/assignments, Updating a Baseline
rescheduling incomplete work, Tracking Timephased Actual Work for Tasks and Assignments
saving interim plans, Updating a Baseline
saving project baseline, Tracking Progress on Tasks
timephased actuals, Tracking Progress on Tasks and Assignments, Tracking Actual and Remaining Values for Tasks and Assignments
updating baseline plans, Tracking Progress on Tasks and Assignments
project triangle model, Getting Your Project Back on Track, Understanding What Defines a Project
projects, defined, A Guided Tour of Project, A Short Course in Project Management
Properties dialog box, Documenting Tasks and the Project Plan
Properties group (Project tab), Setting Nonworking Days
(see also )
Change Working Time, Setting Nonworking Days, Adjusting Working Time for Individual Resources, Adjusting Working Time for Individual Tasks, Updating a Resource’s Information in a Resource Pool, Updating a Resource’s Information in a Resource Pool
Task Notes, Documenting Tasks and the Project Plan, Documenting Resources
Properties group (Resource tab)
Details button, Documenting Resources, Documenting Resources
Information, Setting Up Resource Availability to Apply at Different Times, Entering Multiple Pay Rates for a Resource
Properties group (Task tab)
Add to Timeline, Customizing the Timeline View
Information, Linking Tasks, Adjusting Task Relationships, Setting Task Constraints, Setting Task Constraints, Adjusting Working Time for Individual Tasks, Changing Task Types

R

Recent command (File tab), The Backstage: Managing Files and Setting Options
Record Macro dialog box, Recording Macros
recording macros, Sharing Custom Elements Between Project Plans
Recurring Task Information dialog box, Setting Up a Recurring Task, Setting Up a Recurring Task
recurring tasks, setting up, Entering Fixed Costs
remaining costs, Checking the Project’s Cost and Finish Date
remaining values for tasks, Updating a Baseline
Rename dialog box, Customizing the Ribbon and Quick Access Toolbar
renumbering tasks, Sorting Project Details
Replace Resource dialog box, Troubleshooting Cost and Resource Problems
Reports dialog box
accessing Overbudget Resources report, Examining Resource Costs
accessing Slipping Tasks report, Identifying Tasks that Have Slipped
displaying available reports, Printing Views, Printing Views: Advanced Options
Reports group (Project tab)
Budget Cost report, Examining Task Costs
Overbudget Resources report, Examining Resource Costs
Overbudget Tasks report, Examining Task Costs
Project Summary report, Identifying Tasks that Have Slipped
Reports dialog box, Printing Views, Customizing and Printing Reports, Identifying Tasks that Have Slipped, Examining Resource Costs, Printing Views: Advanced Options
Resource Cost Summary report, Examining Resource Costs
Slipping Tasks report, Identifying Tasks that Have Slipped
Visual Reports, Identifying Tasks that Have Slipped, Examining Task Costs, Examining Resource Costs, Generating Visual Reports with Excel and Visio
reports/reporting
customizing, Printing Views
defined, Printing Views: Advanced Options
functionality, Printing Views
generating in Excel, Saving to Other File Formats from Project
global templates and, Sharing Custom Elements Between Project Plans
printing, Printing Views, Printing Views: Advanced Options
project status, Identifying Tasks that Have Slipped
stoplight reports, Examining Resource Costs
variance in project costs, Examining Resource Costs
viewing, Printing Views
Visio visual reports, Formatting a Network Diagram View, Saving to Other File Formats from Project
Reset button, Customizing the Ribbon and Quick Access Toolbar
resource allocations
evaluating, Examining Resource Allocations over Time
examining over time, Fine-Tuning the Project Plan
leveling, Interrupting Work on a Task, Examining Resource Allocations over Time, Resolving Resource Overallocations Manually
resolving overallocations, Examining Resource Allocations over Time
viewing in resource pools, Creating a Resource Pool
resource assignments, Controlling Work When Adding or Removing Resource Assignments
(see also )
adjusting, Controlling Work When Adding or Removing Resource Assignments, Adjusting Assignments in the Team Planner View
applying contours to, Delaying the Start of Assignments
applying different cost rates, Applying Contours to Assignments
assigning cost resources, Controlling Work When Adding or Removing Resource Assignments
assigning work resources to tasks, Assigning Resources to Tasks, Assigning Cost Resources to Tasks
controlling work with, Assigning Work Resources to Tasks
delaying start of, Delaying the Start of Assignments
editing values, Applying Contours to Assignments
removing work resources, Controlling Work When Adding or Removing Resource Assignments
starting at specific times, Delaying the Start of Assignments
to recurring tasks, Setting Up a Recurring Task
tracking actual/remaining values, Updating a Baseline
tracking timephased actuals, Tracking Actual and Remaining Values for Tasks and Assignments
updating in sharer plans, Viewing Assignment Details in a Resource Pool
variable consumption rates, Assigning Material Resources to Tasks
viewing capacity, Assigning Material Resources to Tasks
viewing in resource pools, Creating a Resource Pool
resource availability/capacity
defined, Examining Resource Allocations over Time
entering, Setting Up Work Resources
setting up, Fine-Tuning Resource Details
viewing, Assigning Material Resources to Tasks
resource calendars
adjusting working time for tasks, Adjusting Working Time for Individual Tasks
defined, Adjusting Working Time for Individual Resources
examing resource allocations, Fine-Tuning the Project Plan
Max. Units field, Adjusting Working Time for Individual Resources
work resources and, Adjusting Working Time for Individual Resources
resource costs, examining, Examining Task Costs
Resource Form
documenting resources, Documenting Resources
Notes details, Documenting Resources
Task Form and, Assigning Work Resources to Tasks
viewing assignments in resource pools, Viewing Assignment Details in a Resource Pool
Resource Graph view, Examining Resource Allocations over Time, Leveling Overallocated Resources
resource groups
grouping project details, Sorting Project Details
sorting project details, Sorting Project Details
Resource Information dialog box
customizing Max. Units values, Setting Up Resource Availability to Apply at Different Times
entering different pay rates, Setting Up Pay Rates to Apply at Different Times
entering multiple pay rates, Entering Multiple Pay Rates for a Resource
resource leveling
delaying, Examining Resource Allocations over Time
for overallocated resources, Resolving Resource Overallocations Manually
functionality, Leveling Overallocated Resources
split tasks and, Interrupting Work on a Task
Resource Leveling dialog box, Leveling Overallocated Resources
resource management, Adjusting Working Time for Individual Resources
(see also specific types of resources)
adjusting working time individually, Adjusting Working Time for Individual Resources
assigning resources, Assigning Resources to Tasks
collecting actuals, Tracking Timephased Actual Work for Tasks and Assignments
cost information, Entering Resource Pay Rates
documenting resources, Documenting Resources
entering fixed costs, Entering Deadline Dates
entering resource capacity, Setting Up Work Resources
entering resource names, Setting Up Work Resources
entering resource pay rates, Entering Resource Capacity
grouping information, Sorting Project Details
Max. Units field, Setting Up Work Resources
saving project baseline, Saving a Project Baseline
setting up work resources, Setting Up Resources
sorting data, Sorting Project Details
troubleshooting problems, Troubleshooting Time and Schedule Problems
types of resources, Setting Up Resources
resource notes
assignment notes and, Applying Contours to Assignments
defined, Checking the Plan’s Duration
entering, Documenting Resources
pasting graphic images, Copying Project Data to Other Programs
Resource Pool command (Resource tab)
Share Resources, Creating a Resource Pool, Linking New Project Plans to a Resource Pool
Update Resource Pool, Linking New Project Plans to a Resource Pool, Opening a Sharer Plan and Updating a Resource Pool
resource pools
benefits, Creating a Resource Pool
breaking link with project plans, Creating a Resource Pool
creating, Creating a Resource Pool
dedicated, Creating a Resource Pool
functionality, Creating a Resource Pool
linking project plans, Updating All Plans’ Working Times in a Resource Pool
naming conventions, Creating a Resource Pool
opening, Updating a Resource’s Information in a Resource Pool, Linking New Project Plans to a Resource Pool
troubleshooting problems, Linking New Project Plans to a Resource Pool
updating information in, Updating a Resource’s Information in a Resource Pool, Linking New Project Plans to a Resource Pool
updating working times in, Updating All Plans’ Working Times in a Resource Pool
viewing assignment details, Creating a Resource Pool
Resource Sheet view
accessing, Setting Up Resource Availability to Apply at Different Times, Leveling Overallocated Resources, Sorting Project Details
copying project data, Copying Project Data to Other Programs
creating resource pools, Creating a Resource Pool
depicted, Views: Working with Schedule Details the Way You Want
documenting resources, Documenting Resources
Entry table, Sorting Project Details
examining resource costs, Examining Task Costs
grouping information, Grouping Project Details
leveling resources, Leveling Overallocated Resources
linking project plans, Linking New Project Plans to a Resource Pool
Resource Form, Documenting Resources
Resource Information dialog box, Entering Multiple Pay Rates for a Resource
setting up cost resources, Setting Up Cost Resources
setting up material resources, Setting Up Material Resources
setting up resources, Setting Up Work Resources
sorting, Sorting Project Details
Std. Rate field, Entering Resource Pay Rates
troubleshooting problems, Troubleshooting Time and Schedule Problems
Resource tab, The Ribbon and Tabs: Finding the Features You Want
(see also )
functionality, The Ribbon and Tabs: Finding the Features You Want
Level group, Leveling Overallocated Resources
Properties group, Documenting Resources, Documenting Resources, Setting Up Resource Availability to Apply at Different Times, Entering Multiple Pay Rates for a Resource
Resource Usage view
depicted, Views: Working with Schedule Details the Way You Want
evaluating resource allocation, Examining Resource Allocations over Time, Examining Resource Allocations over Time
examining resource costs, Examining Resource Costs
functionality, Views: Working with Schedule Details the Way You Want, Delaying the Start of Assignments
hiding assignment details, Printing Views: Advanced Options
linking project plans, Linking New Project Plans to a Resource Pool
Next Overallocation button, Examining Resource Allocations over Time
resolving resource overallocations, Resolving Resource Overallocations Manually
ScreenTips in, Examining Resource Allocations over Time
scrolling horizontally, Examining Resource Allocations over Time
tracking timephased work, Tracking Timephased Actual Work for Tasks and Assignments
viewing assignments in resource pools, Creating a Resource Pool
viewing resource capacity, Viewing Resource Capacity
Resource Views group (View tab), Setting Up Resource Availability to Apply at Different Times
(see also )
Other Views, Examining Resource Allocations over Time
Resource Usage, Views: Working with Schedule Details the Way You Want, Viewing Resource Capacity, Creating a Resource Pool
Team Planner, Adjusting Assignments in the Team Planner View
viewing other views, Views: Working with Schedule Details the Way You Want
Respect Links command (Task tab), Linking Tasks
ribbon interface
as toolbar replacement, Introducing Project
customizing, Editing Macros
finding features, The Ribbon and Tabs: Finding the Features You Want
group divisions, Introducing Project
overview, Introducing Project

S

Save & Send command (File tab), The Backstage: Managing Files and Setting Options, Printing Views: Advanced Options
Save As command (File tab)
editable formats, Identifying Tasks that Have Slipped
functionality, The Backstage: Managing Files and Setting Options, The Backstage: Managing Files and Setting Options, Customizing the Gantt Chart View
Save command (File tab), Introducing Project
saving
interim plans, Updating a Baseline
project baseline, Tracking Progress on Tasks
to other file formats, Opening Other File Formats in Project
Schedule group (Project tab), Saving a Project Baseline, Updating a Baseline
Schedule group (Task tab)
100% Complete, Entering a Task’s Completion Percentage
50% Complete, Entering a Task’s Completion Percentage
Inactivate, Inactivating Tasks, Troubleshooting Scope-of-Work Problems
Indent Task, Organizing Tasks into Phases
Link Tasks, Linking Tasks, Switching Task Scheduling from Manual to Automatic
Mark on Track button, Entering Actual Values for Tasks
Respect Links, Linking Tasks
Split Task, Interrupting Work on a Task
Update Tasks, Tracking a Project as Scheduled, Entering Actual Values for Tasks, Editing Macros
Schedule table, Viewing the Project’s Critical Path
scheduling formula, Assigning Work Resources to Tasks, Adjusting Working Time for Individual Tasks
ScreenTips
assignment dates, Examining Resource Allocations over Time
calendar details, Adjusting Working Time for Individual Tasks
describing work contours, Applying Contours to Assignments
displaying date values in, Applying Contours to Assignments, Tracking Timephased Actual Work for Tasks and Assignments
displaying progress, Entering a Task’s Completion Percentage
in Gantt Chart view, Examining Resource Allocations over Time, Updating a Baseline
notes displaying in, Documenting Tasks and the Project Plan, Documenting Resources
splitting tasks, Interrupting Work on a Task
viewing constraint details, Setting Task Constraints
Scroll to Task command (Task tab), Customizing the Gantt Chart View, Copying Views, Adjusting Task Relationships
scrolling in Gantt Chart view, Customizing the Timeline View
security considerations, Recording Macros
Selected Tasks command (View tab), Creating Dependencies Between Projects
Set Baseline dialog box
accessing, Updating a Baseline
controlling baseline updates, Updating a Baseline
depicted, Saving a Project Baseline
saving interim plans, Updating a Baseline
SF task relationship (see )
Share Resources dialog box
creating resource pools, Creating a Resource Pool
linking project plans, Linking New Project Plans to a Resource Pool
troubleshooting problems, Linking New Project Plans to a Resource Pool
SharePoint, synchronizing task lists, Generating Visual Reports with Excel and Visio
sharer plans
consolidating information in, Creating a Resource Pool
defined, Creating a Resource Pool
opening, Linking New Project Plans to a Resource Pool
troubleshooting problems, Linking New Project Plans to a Resource Pool
updating assignments in, Viewing Assignment Details in a Resource Pool
updating working times in resource pools, Updating All Plans’ Working Times in a Resource Pool
shortcut menus, accessing, Introducing Project
Show/Hide group (Format tab), Customizing the Gantt Chart View, Consolidating Project Plans
Simple Tracking Start project plan, Saving a Project Baseline
slack (float), Viewing the Project’s Critical Path
Slipped/Late Progress filter, Identifying Tasks that Have Slipped
Slipping Tasks filter, Identifying Tasks that Have Slipped, Identifying Tasks that Have Slipped
SNET constraint type (see )
SNLT constraint type (see )
Sort dialog box
functionality, The Ribbon and Tabs: Finding the Features You Want, Sorting Project Details
re-sorting resources by ID, Examining Resource Costs
sorting project details, Sorting Project Details
Split Task command (Task tab), Interrupting Work on a Task
Split View group (View tab)
Details, Views: Working with Schedule Details the Way You Want, Assigning Work Resources to Tasks, Troubleshooting Time and Schedule Problems, Viewing Assignment Details in a Resource Pool
Timeline check box, Views: Working with Schedule Details the Way You Want, Setting Nonworking Days, Troubleshooting Time and Schedule Problems, Formatting a Timeline View
SS task relationship (see )
Standard base calendar, Adjusting Working Time for Individual Resources, Adjusting Working Time for Individual Tasks
Start menu
All Programs, Copying Views, Saving to Other File Formats from Project
starting Project 2010, A Guided Tour of Project
Start No Earlier Than (SNET) constraint type
defined, Setting Task Constraints
usage examples, Setting Task Constraints, Entering Fixed Costs
Start No Later Than (SNLT) constraint type, Setting Task Constraints
start-to-finish (SF) task relationship, Linking Tasks, Adjusting Task Relationships
start-to-start (SS) task relationship, Linking Tasks, Adjusting Task Relationships, Adjusting Task Relationships
starting Project 2010, A Guided Tour of Project
Statistics dialog box, Troubleshooting Time and Schedule Problems
Status bar
functionality, Introducing Project
highlighting support, Filtering Project Details
Zoom In/Out controls, Examining Resource Allocations over Time
Status group (Project tab), Saving a Project Baseline, Rescheduling Incomplete Work
Std. Rate field, Entering Resource Pay Rates
Stop Recording command (View tab), Recording Macros
stoplight reports, Examining Resource Costs
storing macros, Recording Macros
subprojects, defined, Consolidating Project Plans
subtasks
creating, Organizing Tasks into Phases
defined, Entering a Milestone
deleting, Troubleshooting Scope-of-Work Problems
reports and, Printing Views: Advanced Options
successor tasks, Organizing Tasks into Phases, Adjusting Task Relationships
Summary command (Task tab), Organizing Tasks into Phases
Summary table
accessing, Sorting Project Details
depicted, Sorting Project Details
modifying, Filtering Project Details
summary tasks, Customizing the Timeline View
(see also )
adding to Timeline view, Customizing the Timeline View
creating, Organizing Tasks into Phases
defined, Entering a Milestone
deleting, Troubleshooting Scope-of-Work Problems
displaying, Customizing the Gantt Chart View
displaying as callouts, Customizing the Timeline View
inactivating, Inactivating Tasks
linking, Linking Tasks
on Gantt charts, Formatting and Sharing Your Plan, Customizing the Gantt Chart View
reports and, Printing Views: Advanced Options
scheduling, Entering a Milestone, Viewing the Project’s Critical Path
Switch Windows command (View tab), Sharing Custom Elements Between Project Plans, Sharing Custom Elements Between Project Plans, Viewing Assignment Details in a Resource Pool
synchronizing task lists, Generating Visual Reports with Excel and Visio

T

Table Definition dialog box, Customizing Tables
tables
copying data to other programs, Copying Project Data to Other Programs
creating, Filtering Project Details
customizing, Filtering Project Details
defined, Filtering Project Details
global templates and, Sharing Custom Elements Between Project Plans
manipulating columns, Customizing Tables
Tables command (View tab), Entering Actual Values for Tasks
(see also )
Entry table, Saving a Project Baseline
More Tables, Filtering Project Details
Summary table, Sorting Project Details
Variance, Identifying Tasks that Have Slipped, Identifying Tasks that Have Slipped
Work table, Entering Actual Values for Tasks, Tracking Actual and Remaining Values for Tasks and Assignments, Examining Task Costs
tabs (ribbon interface)
as menu replacements, Introducing Project
finding features, The Ribbon and Tabs: Finding the Features You Want
overview, Introducing Project
task bar, changing colors, Formatting a Timeline View
task calendars, Adjusting Working Time for Individual Tasks
task costs, examining, Examining Task Costs
task durations (see )
Task Form
assigning work resources, Assigning Work Resources to Tasks
changing task default settings, Controlling Work When Adding or Removing Resource Assignments
depicted, Views: Working with Schedule Details the Way You Want
editing values, Views: Working with Schedule Details the Way You Want
Resource Form and, Assigning Work Resources to Tasks
scheduling formula, Assigning Work Resources to Tasks
troubleshooting problems, Troubleshooting Time and Schedule Problems
viewing task types, Changing Task Types
Task Information dialog box
applying calendars to tasks, Adjusting Working Time for Individual Tasks
applying constraints to tasks, Setting Task Constraints
changing task relationships, Adjusting Task Relationships
changing task types, Changing Task Types
entering deadline dates, Entering Deadline Dates
entering notes in, Documenting Tasks and the Project Plan
linking tasks, Linking Tasks
manipulating lead/lag times, Adjusting Task Relationships
marking tasks as milestones, Entering a Milestone
removing constraints, Setting Task Constraints
sharing custom elements, Sharing Custom Elements Between Project Plans
viewing task types, Changing Task Types
Task Inspector pane
constraint details, Setting Task Constraints
functionality, Adjusting Task Relationships
scheduling details, Adjusting Task Relationships
task lists
in other file formats, Opening Other File Formats in Project
synchronizing, Generating Visual Reports with Excel and Visio
task names
entering, Creating a New Project Plan
making visible, Customizing the Timeline View
reformatting visually, Customizing the Gantt Chart View
task notes
accessing, Checking the Plan’s Duration
assignment notes and, Applying Contours to Assignments
entering, Checking the Plan’s Duration
pasting graphic images, Copying Project Data to Other Programs
Task Notes command (Project tab), Documenting Tasks and the Project Plan, Documenting Resources
Task Range filter, Filtering Project Details
task relationships
adjusting, Adjusting Task Relationships
creating, Linking Tasks
critical path and, Setting Up a Recurring Task
defined, Linking Tasks, Adjusting Task Relationships
Task report, Printing Reports: Advanced Options
Task Report dialog box, Printing Reports: Advanced Options
task scheduling
automatic, Entering Durations
constraints and, Setting Task Constraints, Changing Task Types
critical path and, Setting Up a Recurring Task
effort-driven, Controlling Work When Adding or Removing Resource Assignments, Adjusting Working Time for Individual Tasks, Changing Task Types
entering deadline dates, Changing Task Types
identifying potential conflicts, Scheduling Summary Tasks Manually
manual, Creating a New Project Plan, Entering Durations
presentation style and, Customizing the Gantt Chart View
recurring tasks, Setting Up a Recurring Task
rescheduling incomplete work, Tracking Timephased Actual Work for Tasks and Assignments
saving project baseline and, Saving a Project Baseline
scheduling formula, Assigning Work Resources to Tasks, Adjusting Working Time for Individual Tasks
setting nonworking days, Setting Nonworking Days
split tasks and, Interrupting Work on a Task
summary tasks, Entering a Milestone, Viewing the Project’s Critical Path
switching, Switching Task Scheduling from Manual to Automatic
tracking progress, Saving a Project Baseline
troubleshooting problems, Getting Your Project Back on Track
Task Sheet view
accessing, Saving a Project Baseline, Entering Fixed Costs, Checking the Project’s Cost and Finish Date, Filtering Project Details
applying Schedule table, Viewing the Project’s Critical Path
creating tables, Filtering Project Details
examining task costs, Examining Task Costs
functionality, Views: Working with Schedule Details the Way You Want
identifying task slippage, Identifying Tasks that Have Slipped
stoplight reports and, Examining Resource Costs
Task tab, Customizing the Timeline View
(see also , )
Clipboard group, The Ribbon and Tabs: Finding the Features You Want, Copying Views, Identifying Tasks that Have Slipped, Recording Macros, Copying Project Data to Other Programs, Copying Project Data to Other Programs
Editing group, Customizing the Gantt Chart View, Copying Views, Adjusting Task Relationships
Font group, The Ribbon and Tabs: Finding the Features You Want
functionality, The Ribbon and Tabs: Finding the Features You Want
Insert group, Entering Durations, Organizing Tasks into Phases, Setting Up a Recurring Task
Tasks group, Switching Task Scheduling from Manual to Automatic, Adjusting Task Relationships
View group, The Ribbon and Tabs: Finding the Features You Want, Viewing the Project’s Critical Path, Assigning Material Resources to Tasks
task types
changing, Adjusting Working Time for Individual Tasks
effort-driven scheduling and, Adjusting Working Time for Individual Tasks, Changing Task Types
fixed-duration, Adjusting Working Time for Individual Tasks, Applying Contours to Assignments
fixed-unit, Controlling Work When Adding or Removing Resource Assignments, Adjusting Working Time for Individual Tasks, Assigning Material Resources to Tasks
fixed-work, Adjusting Working Time for Individual Tasks
viewing, Changing Task Types
Task Usage view
accessing, Changing Task Types, Tracking Actual and Remaining Values for Tasks and Assignments
adding columns to, Changing Task Types
comparing baseline and scheduled work, Examining Task Costs
examining resource costs, Examining Resource Costs
functionality, Views: Working with Schedule Details the Way You Want, Changing Task Types, Delaying the Start of Assignments, Delaying the Start of Assignments
hiding assignment details, Printing Views: Advanced Options
tracking timephased work, Tracking Timephased Actual Work for Tasks and Assignments
vertical divider bar, Tracking Actual and Remaining Values for Tasks and Assignments
viewing variances for assignments, Identifying Tasks that Have Slipped, Examining Task Costs
Task Views group (View tab)
Calendar, The Ribbon and Tabs: Finding the Features You Want, Formatting a Calendar View
Gantt Chart button, The Ribbon and Tabs: Finding the Features You Want, Views: Working with Schedule Details the Way You Want, Saving a Project Baseline, Setting Up a Recurring Task, Viewing the Project’s Critical Path, Updating a Baseline
Network Diagram, Formatting a Network Diagram View
Other Views, Views: Working with Schedule Details the Way You Want, Saving a Project Baseline, Entering Fixed Costs, Leveling Overallocated Resources, Filtering Project Details, Customizing Views
Task Usage, Changing Task Types, Tracking Actual and Remaining Values for Tasks and Assignments
tasks, Controlling Work When Adding or Removing Resource Assignments
(see also , )
Actions button, Controlling Work When Adding or Removing Resource Assignments
adjusting working time, Adjusting Working Time for Individual Tasks
assigning cost resources to, Controlling Work When Adding or Removing Resource Assignments
assigning fixed costs to, Entering Fixed Costs
assigning material resources to, Assigning Material Resources to Tasks
assigning work resources to, Assigning Resources to Tasks, Assigning Cost Resources to Tasks
associating costs with, Entering Fixed Costs
bottom-up planning, Organizing Tasks into Phases
changing default settings, Controlling Work When Adding or Removing Resource Assignments
completion percentages, Saving a Project Baseline, Tracking a Project as Scheduled
controlling work calculations, Assigning Work Resources to Tasks
defined, Creating a Task List, Creating a New Project Plan
defining for deliverables, Entering Task Names
documenting, Checking the Plan’s Duration
entering actual values, Saving a Project Baseline, Entering a Task’s Completion Percentage
entering deadline dates, Changing Task Types
filtering project details, Grouping Project Details
grouping project details, Sorting Project Details
hyperlinking to information, Documenting Tasks and the Project Plan
identifying slippage, Viewing and Reporting Project Status
inactivating, Scheduling Summary Tasks Manually
increasing durations for, Controlling Work When Adding or Removing Resource Assignments
interrupting work, Interrupting Work on a Task
linking, Organizing Tasks into Phases
linking between projects, Consolidating Project Plans
marking as milestones, Entering a Milestone
on critical path, Viewing the Project’s Critical Path
on Gantt charts, Formatting and Sharing Your Plan
organizing into phases, Entering a Milestone
predecessor, Organizing Tasks into Phases
reactivating, Inactivating Tasks
recurring, Entering Fixed Costs
removing working resources from, Controlling Work When Adding or Removing Resource Assignments
renumbering, Sorting Project Details
resassigning, Adjusting Assignments in the Team Planner View
rescheduling incomplete work, Tracking Timephased Actual Work for Tasks and Assignments
resource leveling and, Interrupting Work on a Task, Leveling Overallocated Resources
selecting quickly, Changing Task Types
setting constraints, Adjusting Task Relationships
setting nonworking days, Setting Nonworking Days
sorting project details, Sorting Project Details
splitting into segments, Interrupting Work on a Task, Applying Contours to Assignments
successor, Organizing Tasks into Phases
top-down planning, Organizing Tasks into Phases, Scheduling Summary Tasks Manually
tracking actual/remaining values, Updating a Baseline
tracking timephased actuals, Tracking Actual and Remaining Values for Tasks and Assignments
updating baselines, Updating a Baseline
Tasks group (Task tab)
Auto Schedule, Switching Task Scheduling from Manual to Automatic
Inspect, Adjusting Task Relationships
Mode, Switching Task Scheduling from Manual to Automatic
Team Planner view, Adjusting Assignments in the Team Planner View, Examining Resource Allocations over Time
templates
creating project plans, Creating a New Project Plan
global, Sharing Custom Elements Between Project Plans
sources of, The Backstage: Managing Files and Setting Options
viewing available, The Backstage: Managing Files and Setting Options
text boxes
attaching to Gantt bars, Drawing on a Gantt Chart
attaching to timescale, Drawing on a Gantt Chart
Text group (Format tab), Formatting a Gantt Chart View
Text Styles button (Format tab), Formatting a Gantt Chart View
time considerations (see )
Timeline view
adjusting horizontal divider, Customizing the Timeline View
checking plan duration, Setting Nonworking Days
copying, Drawing on a Gantt Chart
customizing, Customizing the Gantt Chart View
formatting, Formatting a Gantt Chart View
functionality, Views: Working with Schedule Details the Way You Want, Customizing the Gantt Chart View, Customizing the Timeline View
hiding, Views: Working with Schedule Details the Way You Want, Formatting a Timeline View
pan and zoom controls, Customizing the Timeline View
Print Preview option, Printing Views
printing, Copying Views, Printing Views: Advanced Options
timephased fields
functionality, Saving a Project Baseline
peak units, Adjusting Working Time for Individual Tasks
tracking actuals, Tracking Progress on Tasks and Assignments, Tracking Actual and Remaining Values for Tasks and Assignments
timescale
attaching text boxes to, Drawing on a Gantt Chart
changing in Gantt Chart view, Customizing the Timeline View
contouring assignments, Applying Contours to Assignments
graphing allocations against, Examining Resource Allocations over Time
Timescale box (View tab)
adjusting, Views: Working with Schedule Details the Way You Want
Days, Adjusting Assignments in the Team Planner View, Examining Resource Allocations over Time, Resolving Resource Overallocations Manually
Months, Viewing Resource Capacity, Examining Resource Allocations over Time
Thirds of Months, Recording Macros
Weeks, Adjusting Assignments in the Team Planner View, Examining Resource Allocations over Time, Updating a Baseline, Tracking Timephased Actual Work for Tasks and Assignments, Identifying Tasks that Have Slipped, Troubleshooting Time and Schedule Problems, Formatting a Gantt Chart View
Timescale dialog box (Gantt Chart view), Entering a Task’s Completion Percentage
toolbars
Quick Access toolbar, Introducing Project, Editing Macros
ribbons as replacements, Introducing Project
Tools menu, Setting Up a Recurring Task
top-down planning, Organizing Tasks into Phases, Scheduling Summary Tasks Manually
total slack, Viewing the Project’s Critical Path
Tracking Gantt view
accessing, The Ribbon and Tabs: Finding the Features You Want, Updating a Baseline
formatting, Applying Advanced Formatting and Printing
Gantt Chart view and, Applying Advanced Formatting and Printing
identifying task slippage, Identifying Tasks that Have Slipped
updating baselines, Updating a Baseline
viewing tasks with variance, Identifying Tasks that Have Slipped
tracking projects (see )
Tracking table, accessing, Entering Actual Values for Tasks
troubleshooting problems
cost and resources, Troubleshooting Time and Schedule Problems
resource pools, Linking New Project Plans to a Resource Pool
scope-of-work issues, Troubleshooting Cost and Resource Problems
sharer plans, Linking New Project Plans to a Resource Pool
time and resource, Getting Your Project Back on Track
Trust Center dialog box, Opening Other File Formats in Project, Saving to Other File Formats from Project

V

variable consumption rates, Assigning Material Resources to Tasks
variance, Troubleshooting Time and Schedule Problems
(see also )
defined, Tracking Progress on Tasks and Assignments
examining resource costs, Examining Task Costs
examining task costs, Examining Task Costs
identifying, Identifying Tasks that Have Slipped
reporting for project costs, Examining Resource Costs
Variance table
accessing, Saving a Project Baseline, Identifying Tasks that Have Slipped
identifying task slippage, Identifying Tasks that Have Slipped
viewing tasks with variance, Identifying Tasks that Have Slipped
VBA (see )
VBA Editor, Editing Macros
View Definition dialog box, Customizing Views
View group (Task tab)
functionality, The Ribbon and Tabs: Finding the Features You Want
Gantt Chart, Assigning Material Resources to Tasks
other views, Viewing the Project’s Critical Path
View label, Introducing Project
View shortcuts, Introducing Project
View tab, Identifying Tasks that Have Slipped
(see also , , , , )
functionality, The Ribbon and Tabs: Finding the Features You Want
Macros group, Recording Macros, Recording Macros, Editing Macros, Editing Macros
New Window, The Ribbon and Tabs: Finding the Features You Want
Sort, The Ribbon and Tabs: Finding the Features You Want
Split View group, Troubleshooting Time and Schedule Problems
Window group, Sharing Custom Elements Between Project Plans, Sharing Custom Elements Between Project Plans, Creating a Resource Pool, Viewing Assignment Details in a Resource Pool, Consolidating Project Plans
View toolbar, Views: Working with Schedule Details the Way You Want
views
applying in views, Filtering Project Details
copying, Drawing on a Gantt Chart
customizing, Customizing Tables, Sharing Custom Elements Between Project Plans
customizing Gantt Chart view, Formatting and Sharing Your Plan
customizing Timeline view, Customizing the Gantt Chart View
defined, The Ribbon and Tabs: Finding the Features You Want
filtering support, Filtering Project Details
global templates and, Sharing Custom Elements Between Project Plans
grouping information, Sorting Project Details
printing, Copying Views, Printing Views: Advanced Options
reports and, Printing Views: Advanced Options
Visio visual reports, Formatting a Network Diagram View, Saving to Other File Formats from Project
Visual Basic for Applications (VBA) (see )
visual reports
Budget Cost report, Examining Task Costs
Excel supported, Generating Visual Reports with Excel and Visio
Resource Cost Summary report, Examining Resource Costs
status-focused, Identifying Tasks that Have Slipped
Visio supported, Formatting a Network Diagram View, Saving to Other File Formats from Project
Visual Reports dialog box
Budget Cost report, Examining Task Costs
generating reports, Generating Visual Reports with Excel and Visio
Resource Cost Summary report, Examining Resource Costs
status-focused reports, Identifying Tasks that Have Slipped

W

WBS (see )
Window group (View tab)
Arrange All, Creating a Resource Pool
New Window, The Ribbon and Tabs: Finding the Features You Want, Consolidating Project Plans
Switch Windows, Sharing Custom Elements Between Project Plans, Sharing Custom Elements Between Project Plans, Viewing Assignment Details in a Resource Pool
WordPad, Copying Views, Copying Project Data to Other Programs
Work Breakdown Structure (WBS), Formatting a Network Diagram View
work resources
adjusting assignments, Controlling Work When Adding or Removing Resource Assignments
adjusting time for, Adjusting Working Time for Individual Resources
applying pay rates at different times, Entering Multiple Pay Rates for a Resource
assigning to tasks, Assigning Resources to Tasks, Assigning Cost Resources to Tasks
controlling work calculations, Assigning Work Resources to Tasks
costs incurred with, Controlling Work When Adding or Removing Resource Assignments
defined, Setting Up Resources, Fine-Tuning the Project Plan
entering names, Setting Up Work Resources
equipment resources, Setting Up Work Resources
examing resource allocations, Fine-Tuning the Project Plan
multiple pay rates, Entering Multiple Pay Rates for a Resource
resource calendars and, Adjusting Working Time for Individual Resources
setting nonworking days, Setting Nonworking Days
setting up, Setting Up Resources
updating working times in resource pools, Updating All Plans’ Working Times in a Resource Pool
Work table
accessing, Entering Actual Values for Tasks
changing details in, Tracking Actual and Remaining Values for Tasks and Assignments, Tracking Actual and Remaining Values for Tasks and Assignments
components, Entering Actual Values for Tasks
displaying work variance, Examining Task Costs
work units (scheduling formula), Assigning Work Resources to Tasks, Adjusting Working Time for Individual Tasks
..................Content has been hidden....................

You can't read the all page of ebook, please click here login for view all page.
Reset